DOE CD REVIEW

  • from detector part all went very well - no critical questions
  • recommendations: green light to proceed to approval CD3A - approved to go ahead with long lead procurement
  • finalize services (cables, piping, etc.)
  • Procurement of crystal has started - unless updates from NSF have to go ahead with Project process in about two weeks
  • Check in with NSF on
  • SiPMs: only those for the forward calorimeter go through CD3A, the rest through a later procurement schedule


DISCUSSION ON CRYTUR SIPM READOUT PRESENTATION AT IEEE/VANCOUVER

Simulate light distribution from crystal at the back of the crystal to determine the nonuniformity of the light