General EEEMCal Meeting Summary 12/8/23
Jump to navigation
Jump to search
Participants: Sasha, Carlos, Dmitry, Douglas, Crytur-USA, Hrachya, Josh, Tanja, Justin, Patrick Moran, Renee, Richard, Casey, Vardan, Julie
NSF MSRI
- Under internal review at NSF
- Action item: follow up with NSF if possible to get a timline for the decision process - going into the new year people are making plans for the outyears
READOUT/ELECTRONICS
- Coordination of SiPM purchases
- idea is to procure 100 SiPMs of four different types:
- S14160-6015PS: 6x6 mm2, 15um pitch
- S14160-3010PS: 6x6 mm2, 10um pitch
- S14160-3015PS: 3x3 mm2, 15um pitch
- S14160-3010PS: 3x3 mm2, 10um pitch
- Costs are $110/unit for 1-99 quantity and $58/unit for 100-200 quantity
- For making the decision may not need 100 SiPMs - could plan
- Action items:
- Justin makes list of SiPMs needed
- Olivier/Irina check if can set up a meeting with Hamamatsu rep to make aware of large order and if they can provide few SiPMs to test at favorable pricing
- Coordination of SiPM irradiation
- Justin checking at UMass-Lowell
- Tanja check with Giessen U.
- Renee check at UKY
- Test beam opportunities
- JLab available in fall 2024 - electron beam
- MAMI electron beam
- LHC test beam lines - mixed beams; already scheduled beam time for forward calorimeter (April/May 2024)
- DESY - may be available after July 2024 - to send equipment there order of $3000 each way
- Fermilab - down for one year
- Action item: come back to this in January - more detail on each facility and planning for what is needed
MECHANICAL DESIGN
- Next meeting maybe a update
- Ongoing studies on stability, thermal design, etc.
EIC PROJECT
- Start preparing procurement documents - Sasha will contact with needed documents
NEXT MEETING: FRIDAY 22 DECEMBER AT 8AM ET