General EEEMCal Meeting Summary 6/14/24

From Cuawiki
Jump to navigation Jump to search

PARTICIPANTS: Carlos, Sasha, Douglas, Ethan Cline, Gerard, Ioana, Justin, Larry, Michael Finger, Mirek Finger, Renee, Vardan, Crytur, Tanja, Dmitry, Hamlet, Nathan Grau,

DESY TEST BEAM PREPARATIONS

  • Offically approved for 28 October - 11 November
  • no rush to disassemble
  • Douglas is the contact for the run
  • Need to know who is coming - Douglas has to invite them and then they can register
  • from MIT Ethan Cline, Ivica, and Douglas are coming
  • No more than 5 people in the counting house, but more people can be in the test area
  • About 6 people for assembly/disassembly is a good number
  • Shipping equipment: follow the instructions for import/export
  • check the rules for EU countries - if no special import requirements, then can go straight to the relevant building
  • Initial count:
  • Orsay: 1-2
  • Crytur: 2-3
  • AANL: 1-2 (pending funding)
  • CUA: 1
  • Prepare a SiPM readout to use with the MIT prototype
  • running w/ Doug's readout connected to SiPM's? For a *direct* comparison of PMT to SiPM
  • Digitizer CAEN 1725S
  • five extra crystals that could be the SiPM spare modules
  • PED for final design - note: these funds can be used even after the final design review planned for Nov/Dec 24 or Jan 25
  • should be for long-term, about one year
  • may include funds for pre-production
  • for both labor and materials
  • process takes about 3 months before funding becomes available
  • Actions:
  • Groups send personnel info for DESY beam test to Douglas
  • Groups start preparing lists of hardware that will be brought to DESY
  • Funding options for SiPM purchase for DESY beam test - need order of 400


NEXT MEETING: FRIDAY 28 JUNE AT 8:00AM ET