General Meeting Summary 6/30/22
Jump to navigation
Jump to search
PARTICIPANTS: Aaron Brown, Alexandre Camsonne, Fernando Barbosa, Bogdan Wojsekhowski, Brad Sawatzky, Carlos Munoz-Camacho, Deb Biswas, Erik Wrightson, Hamlet Mkrtchyan, Julie Roche, Steven Lassiter, Marie Boer, Mark Jones, Paul King, Abishek Karki, Paulo Medeiros, Vardan Tadevosyan, Vladimir Berdnikov, Tanja Horn, Pramita Tiwari
ASSEMBLY UPDATES
- Crystal stacking
- viewing photos of NPS during assembly - one taken at same angle as the mechanical drawing
- Cabling
- presently 4 columns are fully cabled and PCBs installed
- time for installation: 2 columns/day - 2 people can work, need to take shifts
- cabling the remaining 26 columns would take 3 weeks total
- cosmic paddles are installed and connectors - HV and signal cables need to be connected to the paddles
- Ongoing:
- cabling on top part (PS, DAQ, LED controls, LV)
- connect HV and signal cables and PS for fans
- DAQ/Cables/Infrastructure - 80% moved into EEL-108 and cables being bundled
- The team: Hamlet, Vardan, Pramita, Erik
- God progress - to date 200 cables bundles
- Discussion about moving NPS equipment out of the HD cleanroom area with target date July 6th
- NPS detector stays in its area
- crates can be disposed of
- HV cables complete in EEL126 - ready to go
- LV cables - being put together (Fernando and team)
ASSEMBLY PLANNING
- Finishing the cabling of 26 remaining columns
- Orsay team could come to finish up cabling
- in preparation need to do PMT assembly
- Preparation of PMTs
- put PMT together with HV divider and put sticker on it
- Orsay team can then do the more detailed assembly
- plan to complete PMT preparation by end of August
- Maintenance of detector
- anyone can participate and be training in the assembly of columns
- contact Carlos to schedule
- Turning on the HV and start tests
- plan to hook up the 4 columns into the DAQ before the end of July
- PMT checkout with scope
- plug into DAQ
- check out system with DAQ
- run and read all instrument analysis and controls (chiller, temp, etc.)
- Brad should be there for initial HV turning on
- Check of HV cables
- continuity check - was done for inside cables
- recommendation: do visual inspection for outside cables
- have some spare cables as needed
DSG UPDATES (Aaron)
- EPICS PHOEBUS screen development - monitoring and control screens for both chiller and thermal readback
- can be rolled out as soon as next week for checking out the readbacks before turning on the HV
- ready to run on Linux - software environment should be compatible
- System to run on is cdaql3 - start staging software there
- Configuration file control
- Ansys thermal analysis
- investigate how heat propagates along crystals
- Cables for scintillator paddles: all parts on site except pins; once these arrive assembly can happen
- HV crates
- one is still with the DSG (HallC-1); located in cleanroom in front of EEL-108
- LED control GUI
- setup is done, need to do programming
- Action Items:
- install HV controls and GUI on cdaql3 and test
- LED control GUI programming - set up meeting with Brad
- LED ribbon cable connectors - crimp on connectors - contact Amrit about the task (Brad)
MECHANICAL UPDATES (Paulo)
- New beamline procurement
- proceed with small angle beamline
- wait with larger angle beamline procurement for simulation results
DAQ/ELECTRONICS/SOFTWARE
- Critical path: event unblocking - ongoing discussions with David H. about possible options
- For detector checkout all is in end
- modified firmware etc. will be checked
- need to go through the full chain
- Grounding and tests of ground
- ground connector on HV divider
- ground on frame is available but not planning to connect it - are there any tests that could be done to verify that it is not needed before columns cabling is finished?
- start with a clean setup for baseline
- next check noise pickup, e.g., plug in a number of noise devices and see if pickup exists
NEXT MEETING: THURSDAY 21 JULY 2022 AT 9:00AM ET