General Meeting Summary 6/9/22
Jump to navigation
Jump to search
PARTICIPANTS: Paulo, Tanja, Vardan, Vladimir, Aaron, Hamlet, Brad, Rolf, Bogdan, Abishek, Pramita, Carlos, Alexandre, Julie, Hakob, Marie, David H
CRYTAL MODULE PREPARATION (Vladimir)
- Team of 7 people (Vladimir, Abishek, Hamlet, Josh, Petr, Vardan, Zheng) from 4 institutions (AANL, CUA, UIC, MSU)
- Completed the crystal module preparation during the month of May
- 1100 crystals
- team worked every day of the month for the entire day
- All but 100 crystals were prepared in RM 126 - 100 crystals prepared in NPS cleanroom
- Crystals were stored on shelves in the NPS assembly area
- all labeled from 1-1100
CRYSTAL STACKING (Carlos)
- Frame prepared
- 19 rows out of 36 were stacked, expect other half to be ready by Friday afternoon
- Next step: PMT assembly
- done column by column - all cables installed on each PMT
- Reason for not fully parallelizing PMT assembly with stacking: one crate that was sent from Orsay was delayed and only received this week - low voltage and some tools needed for assembly were in it
- Next week: start cabling - anticipate cabling complete for a few columns before Orsay group leaves
- Orsay team can return in September to finish cabling or for further tests (cooling, electronics, etc.)
- Action items:
- organize meeting on Thursday 6/16 at 9AM ET to discuss path forward, e.g., cabling after Orsay team leaves, possible detector checkout, etc.
MECHANICAL DESIGN/ENGINEERING (Paulo)
- SHMS/NPS installed/fitup
- platform completely installed and removed
- new detector deck section installed permanently
- Detector frame assembled
- Detector box installed onto detector frame and detector assembly ongoing by Orsay team
- lifting fixture expected in July
- beamline 1 (run group 1 - go to small angle) under physcis review and ready for fabrication
- beamline 2 (run group 2 - reduce radiation) under physics review, some changes requested, and ready for fabrication
- Items left to do:
- target pivot reinforcement
- cabling and cable management
- Action items:
- check on if any magnetic items in NPS frame
UPDATES FROM DSG (Aaron)
- CAEN HV Controls and Monitoring
- Labview hardware interlock program development
- temperature and humidity sensor
- dew point
- etc.
- LED graphical programming ongoing
- HV cables
- tested and podded
- 21 ready for cabling - can be moved from 126 to 108
- Action items:
- check on HV cables - ok to move cables from 126 to 108
- LED graphical programming
DAQ/ELECTRONICS AND SOFTWARE (David H, Brad)
- Main effort centered on updating HCANA to be compatible with MOD10 (full waveform) data
- data from PionLT used for setting up and testing
- Other efforts
- replay script
- database
- Moving DAQ/electronics equipment into RM108 for setting up the DAQ
- HV and power supplies
- HV cables are in 126
- power supplies etc in ESB
- LV power supply in 126 along with carts
- cabling and connectors on site - some cables still need to be assembled
- LEDs on each PMTs - LED boards are ready
- Need good oscilloscope in 108 - there is one available and planned to be moved there
- Action items:
- continue checking off items from list
GENERAL DISCUSSION
- Action item: make checklist to review action items to make sure that nothing forgotten
- impact on NPS magnet on HMS optics
- NPS frame magnetic/nonmagnetic
- looks like aluminum
- check if steel (bolts etc.)
- seems all on frame is nonmagnetic
- Mailing lists have been setup: nps and nps-daq mailing lists
- no action needed for current collaborators
- if new students/collaborators please sign up through JLab mailing lists
- Talk at Hall A/C meeting on June 16th and June 17th
- Propose one 40min long talk on both detector and physics
- start the talk with assembly acivities to show all the progress
- talk might have ~10 slides on physics upcoming and new proposed (ask experiments to provide one slide each - there will also be full talks on these proposals later in the workshop)
- speaker: Vladimir Berdnikov
- Talk with focus on new opportunities with NPS (DDVCS, etc.) at Workshop at VTech on July 18-22
- Abstract submission still open
NEXT MEETING: THURSDAY JUNE 30TH AT 9AM ET