General Meeting Summary 7/21/22
Jump to navigation
Jump to search
PARTICIPANTS: Hamlet Mkrtchyan, Yeranuhi Gavilyan, Brad Sawatzky, Arshak Asaturyan, Vladimir Berdnikov, Tanja Horn, Carlos Munoz-Camacho, Fernando Barbosa, Paulo Medeiros, Ye, Zhenyu, Rolf Ent, Abishek Karki, Charles Hyde, Pramita Tiwari, Vardan Tadevosyan
NPS ASSEMBLY - INITIAL PMT CHECKOUT (Brad, Pramita, Fernando, Chris, et al.)
- put together baseline software and hardware systems and able to take a first look at a couple NPS PMTs
- needed to reconfigure the MPOD module for the slow regulation for the 150 foot cable.
- There seems to be a problem with at least 1 of the 4 connected LV distribution boards.
- Focusing on the first column of cells, the current draw for that LV board matched the 18mA/ base prediction and everything behaved reasonably well.
- Ramped up HV on one PMT while watching the scope with a small effective threshold (relative to the noted baseline). Current
draw on the HV supply at 600V was 400--405 uA -- exactly what was projected.
- Saw ~30mV level cosmics pulses on the 3 PMTs looked at with the HV at 700V. This is consistent with what wase expected from Vlad's studies.
- There is some significant 20--30mV level, high frequency noise present on the baseline right now. Grounding is not yet optimal, so:
- will go through the other LV boards/connections tomorrow and locate what is driving the higher than expected current draw.
- operate PMTs at up to 800 V to pull out the noise - should be safe for the 8-stage biasing for tests. For normal operation, HV=605 @ 405 uA, nominally, to limit the anode current
- Action items:
- understand noise and try to reduce/eliminate it
- plan is to finish the setup for the four columns by end of the month
ELECTRONICS
- Major item being addressed is event unblocking
- Diagnostic tools will be available for detector checkout - based on existing tools and adapted by Pramita/Julie
DSG UPDATES (Aaron)
- High Voltage Settings GUI - allows for setting parameters for all CAEN modules/channels
- EPICS screens development for monitoring - debugging and optimizations
- Chiller testing - communication and flow meter testing; plan to start next week
- Started process of installing applications for monitoring etc. on Hall C computers, but encountered difficulties
NPS MECHANICAL (Paulo)
- Detector lift fixtures and rail section
- presently being painted and will be delivered by the end of the month
- Cable carrier/guide evaluation
- cable bundles on dollies seems to be the best option for NPS - carrier might become to large and heavy
- NPS beam pipe 1 out for procurement
- beam-line 2 is under physics review
NPS PLANNING
- Plan for cabling and PMT final assembly etc.
- IJCLab-Orsay team plans to arrive in second half of September and team members will be on site for 1-1.5 months to complete the tasks and possibly contribute to detector checkout
- helpful to have initial PMT assembly ready
- Initial PMT assembly (AANL team, Vladimir)
- AANL team will lead the initial PMT assembly as soon as the space is available - need a table - perhaps Mezzanine would be a good place?
- additional contributors welcome! Please contact Tanja/Brad/Vladimir
- Near term cabling needs to be complete
- presently the team responsible is: AANL team, Pramita, Erik, Abishek
- Action item:
- update Gantt chart looking forward to the next year
- include bullet points with tasks (also include administrative steps towards the Phase 1 experiments like any needed review)
- PAC50
- DVCS on neutron approved - next steps: contact Patrizia if ERR needed and submit beam time request
- TCS experiment deferred for opportunity to demonstrate experiment design
NEXT MEETING: THURSDAY 25 AUGUST AT 9AM ET