Meeting Summary Notes
Jump to navigation
Jump to search
NPS COLLABORATION MEETING - FEBRUARY 1-2, 2021
HALL C UPDATE (Steve)
- HMS status
- many detectors have been refurbished
- dipole momentum range up to 7.4 GeV/c (high-end momentum range of HMS) - may need to rope off platform at high fields
- First opportunity to run NPS Phase-1 in 2023 (E12-13-010/E12-13-007 and E12-06-114 additional DVCS days moved from Hall A)
- Estimated time to install NPS start to finish: 3-4 month assuming pre-installation tasks have been done ahead of time
- HB removal ~ 2 weeks
- Target foes not have to be removed to install the NPS (see page 4 of Paulo's talk
- Action item:
- check on plans for testing HMS hodoscope paddle in magnetic field
- detailed installation plan
- check what is needed formally to add E12-06-114 to the run plan, e.g., amendment to ERR 2019, submission of beam time request, etc.
MECHANICAL DESIGN (Paulo)
- Much progress with design and procurements
- Biggest challenge at the moment: routing cables to patch panel and accommodating movement for configuration changes
- detector slide cart weight ~3000 lbs - need to determine how to best push it for different detector locations
- Stair case: for any detector support structure that people will stand on need approval from structural engineer - e.g. QWeak platforms in past
- Action items:
- make small table with time estimates for rotating magnet, moving magnet from one side to another, etc.
- Plan any work on target platform before May 2022 (before nuclear target running)
SENSORS/HV BOARDS&CABLES/SLOW CONTROLS (Aaron)
- Much progress - 1100 HV cables were fabricated
- HV cable testing still needs to be done
- Certification of Samtec connectors
- connector rating from manufacturer seems to not match the operational condition with range up to 1100 V
- note: if change connector also need to change HV board
- path forward: test connector up to 1100 V and document the results (DSG)
- Long cables (140' GPW 42cond) will be available over time in the test lab - length selected to be what is needed in Hall C
- Action items:
- test HV cables
- test Samtec connectors and document
DAQ/ELECTRONICS (Brad S.)
- Support hardware
- Cable run - working with Paulo
- Grounding - isolate NPS chassis so that do not contaminate the system
- Reminder of trigger: generated by VTP and masked to select crystals that are part of the cluster
- Cluster trigger 3x3 with row at the seam - going to smaller cluster is possible, but involves significant work
- VTP logic - if find a valid cluster then form trigger
- full waveform for all crystals participating in the cluster (identified by the VTP) will be recorded
- DAQ hardware and firmware/SW
- FADCs are available, but need to coordinate with other projects (e.g. SBS) --> reserve FADCs for NPS
- FADC synching with RF - never been done for FADC, might be an interesting run plan item, but not needed for NPS
- Firmware development ongoing
- Need Analyzer support for event-blocking mode, decoder updates - critical path item
- examples may be available from Compton polarimeter activities
- Slow Controls
- LED board design nearly done - next need to procure and fabricate
- LED control GUI needs to be designed
- NPS Assembly area
- Detector assembly area identified and cleared in the test lab - accross from NPS crystal clean room; some coordination with design and/or Walter's groups
- DAQ in the test lab should be available later in the year
- Action items:
- Document electronics/DAQ items in the Wiki - material that could be of interest in future reviews
- Prepare an assembly plan for CH similar to what was done for mechanical mounting
FEG UPDATES (Chris Cuevas)
- Need to get started on sparsification firmware/SW
- Slow controls
- LED board - should have pulse mode available during regular run
- VME crate should be available for LED drivers
- Action items:
- Start on sparsification firmware - critical path item
- continue all other activities
ANODE CURRENT (Fernando)
- Anode current setup is now ready - next need to develop the procedure to measure anode current
- need personnel from NPS collaboration (2-4 hours/day)
- Action item:
- measure and document anode current - directly related to availability of bases - critical path item
DETECTOR FRAME (Emmanuel)
- Assembly completed in Orsay and frame was shipped to and received at JLab in January
- Detailed NPS mounting plan document was developed
- Note: the final frame for the NPS will be available for the assembly in the test lab
- Add cooling/pressure tests early on, e.g. near day 2
- note: if disassemble and then reassembly tubes have to do a leak check everytime
- May want to add explicitly to check for bubbles in optical grease
- Check of magnetic shielding to be done later - need full field
- Time frame assembly - current estimate: later in the year
- International travel likely not possible until September
- Need availability of and timeframe for components
- Note: NPS assembly moves to Hall C as one unit
- Action items:
- Add cooling/pressure tests, etc. in NPS mounting plan
- Check Kapton tape - isolation configuration
CRYSTAL STACKING (Vladimir, Hamlet, Hakob)
- Estimate to have 1164 Crytur crystals at JLab in August 2021
- some Crytur crystals may be needed for ongoing R&D projects
- there are also on order 400 SICCAS crystals - there are less radiation hard and not as uniform as Crytur crystals
- Crystal stacking strategy: 3 possible options based on October 2020 discussions)
MAGNET MAPPING (Charles)
- Measurements were done up to 250A - see differences betweem Opera calculations vs. data
- Note: measurements were done with main coil only, while Opera assumed both coils (main and corrector)
- could rerun TOSCA model to give confidence that the magnet works
- Magnet steel
- magnet steel predominantly 1010
- steel used: from BNL and additional steel from another JLab magnet
- in general, newer steel may saturate earlier than older steel, but does not seem an issue here
- Overall plan for the magnet:
- Demonstrate it works as advertised
- Fringe fields - to be tested in the hall - need accelerator test plan (HMS optics, beam displacement, etc.)
- Action items:
- Rerun Opera with just the main coil at 250A
- Accelerator test plan (Jay)
SOFTWARE DEVELOPMENT (Carlos Y., Steve)
- Working in NPS clustering algorithm - integration into Hall C Analyzer
- idea is to develop multiple different algorithms to compare
- Other items to be done:
- VTP decoder updates
- solve and implement data unblocking
- merge multi-threaded podd with hcana
- Data unblocking
- There are actual data files (Brad S.)
- Some codes are around, but nothing yet of production quality
- some examples from Compton polarimeter activities from about one year ago are available (Alexandre)
- Waveform analysis
- Orsay has some examples of code
- Data are available from SHMS
- Calibration and monitoring software
- need guidance on how calibrations are done - calibration methods
- Action items:
- Algorithm development
- Multiblock
ASSEMBLY PLAN - ITEMS NEEDED
- Installation plan
- Mechanical mounting plan
- Crystal wrapping plan
- Software test stand and counting house assembly plan
- Cabling maps
- Resources plan - on-site personnel
- Accelerator test plan
CALIBRATION PLAN
- Calorimeter calibration Methods:
- Cosmics
- Elastics
- Exclusive pi0
- LED pulses (LED peak wavelength 465 nm)
- Tests before moving to hall - in general test beforehand as much as possible to identify possible bottlenecks:
- Mu metal shield test - could use Helmholtz coil setup Hall A
- HV calibration PMT
- DAQ/electronics - LED, cluster trigger checking
- Cooling tests
- Slow controls, interlocks
- Tests after moving to hall:
- Mu metal full assembly with magnet on
- Fringe fields
- Calibrations crystal
- DAQ/electronics - OR w/ VTP
WACS - NPS PHASE-2
- There are two WACS experiments: 1) unpolarized (cross section), 2) Polarized WACS (asymmetry, needs also CPS)
- Unpolarized WACS was part of the ERR 2019 - main difference to Phase-1 is the radiator
- For polarized WACS need additional crate for GEM readout
- Action items:
- prepare beam time request for unpolarized WACS
- set milestones for formal ERR request for polarized WACS