(Created page with "DISCUSSION TOPICS: * Simulations Update * Shielding and magnet model * Hall A/C model and design/implementation * Hall D design and radiation simulations * Other") |
|||
(One intermediate revision by one other user not shown) | |||
Line 4: | Line 4: | ||
* Shielding and magnet model | * Shielding and magnet model | ||
+ | ::* [https://wiki.jlab.org/cuawiki/images/7/71/CPS_Initial_Design_Model_8_28_20.pptx CPS Design Model Update] | ||
* Hall A/C model and design/implementation | * Hall A/C model and design/implementation | ||
Line 10: | Line 11: | ||
* Other | * Other | ||
+ | |||
+ | |||
+ | PARTICIPANTS: A. Comer, A. Asaturyan, R. Ent, H. Mkrtchyan, I. Strakovsky, V. Tadevosyan, T. Horn, J. Crafts, S. Dobbs, B. Wojsekhowski, David H., T. Keppel | ||
+ | |||
+ | |||
+ | '''SUMMARY NOTES''' | ||
+ | |||
+ | '''SIMULATIONS''' | ||
+ | |||
+ | * Work ongoing | ||
+ | |||
+ | |||
+ | '''SHIELDING AND MAGNET MODEL''' (Josh) | ||
+ | |||
+ | * Shielding stacked up to top of magnet - plate added on top to make things level | ||
+ | |||
+ | * Openings in front and back of shielding implemented | ||
+ | |||
+ | * Flared downstream end - still need feedback from radiation simulation to finalize | ||
+ | |||
+ | * Inlet of LCW cooling water is on upstream end - in same place as beam pipe | ||
+ | ::* advantageous from radiation point of view: high energy particles go forward (few GeV based on e beam), energy of particles going backward is soft | ||
+ | |||
+ | * Next steps: | ||
+ | ::* Build rest of shield taking into account any feedback on points below | ||
+ | ::* Need for taping on front end | ||
+ | ::* Size of beam pipe and material needed - then can build around and make support structure | ||
+ | |||
+ | ::* Structural support of tungsten powder - need more information on tungsten blocks | ||
+ | ::* Thermal calculation for extension of core in longitudinal direction - work ongoing | ||
+ | |||
+ | |||
+ | '''ENGINEERING/DESIGN''' (Amy) | ||
+ | |||
+ | * Work ongoing, e.g. thermal calculations | ||
+ | |||
+ | * Action item: dimensions of beam pipe, etc. | ||
+ | |||
+ | |||
+ | '''HALL D DESIGN/ENGINEERING''' (Sean) | ||
+ | |||
+ | * Work ongoing on front end | ||
+ | |||
+ | |||
+ | '''PAC48 RECAP''' | ||
+ | |||
+ | * All comments based on close out session - report should be available soon | ||
+ | |||
+ | * Hall D/KLong: | ||
+ | ::* science case well received, some concern about higher level management coordination | ||
+ | |||
+ | * Hall A/C TCS | ||
+ | ::* Science well received | ||
+ | ::* Main comment: need for more information on experimental setup - see if experiment is possible | ||
+ | ::* one issue: GEM as part of trigger - high risk since never done before | ||
+ | ::* one possible option: find out if GEM in SRO works as done for TDIS | ||
+ | ::* '''Action item''': Vardan present current assumptions on trigger | ||
+ | |||
+ | NPS+CPS installation - COMPLEMENTARITY | ||
+ | |||
+ | * So far no objections based on physics | ||
+ | |||
+ | |||
+ | '''NEW CPS PHYSICS EXPERIMENT IDEAS''' (Bogdan) | ||
+ | |||
+ | * Two photon exchange experiment - with photon beam from CPS better intensity, use secondary target downstream plus some detectors - need to work out details | ||
+ | |||
+ | |||
+ | '''NEXT MEETING : FRIDAY 11 SEPTEMBER AT 11AM ET''' |
Latest revision as of 15:54, 28 August 2020
DISCUSSION TOPICS:
- Simulations Update
- Shielding and magnet model
- Hall A/C model and design/implementation
- Hall D design and radiation simulations
- Other
PARTICIPANTS: A. Comer, A. Asaturyan, R. Ent, H. Mkrtchyan, I. Strakovsky, V. Tadevosyan, T. Horn, J. Crafts, S. Dobbs, B. Wojsekhowski, David H., T. Keppel
SUMMARY NOTES
SIMULATIONS
- Work ongoing
SHIELDING AND MAGNET MODEL (Josh)
- Shielding stacked up to top of magnet - plate added on top to make things level
- Openings in front and back of shielding implemented
- Flared downstream end - still need feedback from radiation simulation to finalize
- Inlet of LCW cooling water is on upstream end - in same place as beam pipe
- advantageous from radiation point of view: high energy particles go forward (few GeV based on e beam), energy of particles going backward is soft
- Next steps:
- Build rest of shield taking into account any feedback on points below
- Need for taping on front end
- Size of beam pipe and material needed - then can build around and make support structure
- Structural support of tungsten powder - need more information on tungsten blocks
- Thermal calculation for extension of core in longitudinal direction - work ongoing
ENGINEERING/DESIGN (Amy)
- Work ongoing, e.g. thermal calculations
- Action item: dimensions of beam pipe, etc.
HALL D DESIGN/ENGINEERING (Sean)
- Work ongoing on front end
PAC48 RECAP
- All comments based on close out session - report should be available soon
- Hall D/KLong:
- science case well received, some concern about higher level management coordination
- Hall A/C TCS
- Science well received
- Main comment: need for more information on experimental setup - see if experiment is possible
- one issue: GEM as part of trigger - high risk since never done before
- one possible option: find out if GEM in SRO works as done for TDIS
- Action item: Vardan present current assumptions on trigger
NPS+CPS installation - COMPLEMENTARITY
- So far no objections based on physics
NEW CPS PHYSICS EXPERIMENT IDEAS (Bogdan)
- Two photon exchange experiment - with photon beam from CPS better intensity, use secondary target downstream plus some detectors - need to work out details
NEXT MEETING : FRIDAY 11 SEPTEMBER AT 11AM ET