Difference between revisions of "General EEEMCal Meeting Summary 5/3/24"
Jump to navigation
Jump to search
(Created page with "PARTICIPANTS: Ioana, Richard, Rosi, Miroslav, Tanja, Casey, Douglas, Sasha, Bineta, Carlos, Julie, Justin, Dmitry, Crytur-USA, '''PLANNING TOWARDS SIPM SELECTION''' * Plan...") |
|||
Line 1: | Line 1: | ||
+ | Back to Meeting Main Page --> [https://wiki.jlab.org/cuawiki/index.php/EEEMCal_Meetings Meeting Main] | ||
+ | |||
PARTICIPANTS: Ioana, Richard, Rosi, Miroslav, Tanja, Casey, Douglas, Sasha, Bineta, Carlos, Julie, Justin, Dmitry, Crytur-USA, | PARTICIPANTS: Ioana, Richard, Rosi, Miroslav, Tanja, Casey, Douglas, Sasha, Bineta, Carlos, Julie, Justin, Dmitry, Crytur-USA, | ||
Latest revision as of 09:15, 18 October 2024
Back to Meeting Main Page --> Meeting Main
PARTICIPANTS: Ioana, Richard, Rosi, Miroslav, Tanja, Casey, Douglas, Sasha, Bineta, Carlos, Julie, Justin, Dmitry, Crytur-USA,
PLANNING TOWARDS SIPM SELECTION
- Plan to irradiation test all SiPMs at UCR - all models except for 6010 (Hamamatsu confirmed that there is no difference between 3010 and 6010)
- Justin and Gerard plan to be present at the test
- Developed a plan for the irradiation of the SiPMs
- Expect to be able to make a decision on which SiPM model after the irradiation test, but it will require additional studies as well
- Criteria towards making the decision on the SiPM model
- how much dark current
- geometry
- pixel size
- lowest possible signal
- linearity over dynamic range
- Plan is to start setting up test benches
- Lehigh U. (from scratch), OU (starting from NPS setup), ACU
- ACU has been doing test bench tests (boards and SiPMs)
- goal is to be ready for testing SiPMs for the beam test
- Plan for parallelizing the selection of SiPM for October beam test and final SiPM to make sure that SiPMs are available given the potentially long lead time
- determine the best candidate SiPM based on test bench data available now (time frame ~1 week)
- use this best candidate SiPM and order the needed quantity of that model for the October beam test - estimated cost for SiPMs for the October beam test is ~$20k
- continue test bench studies towards final candidate SiPM over the summer
- decide on final SiPM at the end of the summer
- Action items:
- share the irradiation plan to the group
- develop a procedure for making the decision on the SiPM final candidate
- ask Hamamatsu for current lead time
PLANNING TOWARDS READOUT CHAIN SELECTION
- Details will be discussed in the 9 May meeting
FUTURE PLANNING
- Explore if we can have an update from the engineering team in the EEEMCAL meeting
- Explore options for setting up PDE funds to keep things moving (Sasha)
- Explore with DESY management what is possible in principle at low end, e.g., below 1 GeV (Douglas)
- Explore setting up test benches for crystals
- CUA/JLab has a setup that could be duplicated and used to gain experience
- JMU and UKY need to setup a test bench
NEXT MEETING: FRIDAY 31 MAY AT 8AM ET