Difference between revisions of "General Meeting Summary 1/4/18"

From Cuawiki
Jump to navigation Jump to search
(Created page with "SUBSYSTEM UPDATES MAGNET (Bogdan) * Magnet main coil on the way from New Zealand - anticipated arrival at end of January * Magnet yoke on schedule for delivery end of Janua...")
 
Line 10: Line 10:
  
 
* [https://wiki.jlab.org/cuawiki/images/9/93/TestLabScetch142018.png A sketch of the new test lab space for NPS]
 
* [https://wiki.jlab.org/cuawiki/images/9/93/TestLabScetch142018.png A sketch of the new test lab space for NPS]
::* same dimensions, just in a different location as before
+
::* same dimensions, just in a different location
 +
 
 +
 
 +
HV DIVIDERS (Julie)
 +
 
 +
* Order was placed for 1200 dividers, anticipate 30 day delivery, assembly of a few hundred could be done by summer
 +
* Need sockets for full assembly
 +
::* currently have ~200 PMTs and sockets at JLab (some have been machined from larger size, but all should be ok)
 +
::* option to procure all sockets this year to finalize full assemblies by next year fall
 +
 
 +
 
 +
FRAME (Carlos)
 +
 
 +
* Planning to present design options at the collaboration meeting and to discuss possible optimizations. IPNO engineer/designer will also meet with Mike Fowler.
 +
 
 +
 
 +
CRYSTALS (Carlos, Rong, Vladimir, TH)
 +
 
 +
* Granite table ready for dimension measurements at JLab
 +
 
 +
* IPNO setting up for crystal characterization measurements, carried out tests at Giessen U. for inter-laboratory comparison - data analysis ongoing
 +
 
 +
* Microscopy and chemical composition analysis were carried out for 12 crystals at CUA.
 +
::* chemical composition determined with XRF, statistical analysis suggests that both, stoichiometry and addition of other elements have an impact on optical properties, more detailed analysis ongoing
 +
 
 +
* Optical measurements continuing at CUA
 +
 
 +
 
 +
PMTs (Vladimir, A. Somov)
 +
 
 +
* PMT characterization setup at JLab - fixed light leaks of dark box in the process
 +
 
 +
* 65 PMTs were tested, all with the same divider
 +
::* HV scan, measured amplitudes - looks good at first glance
 +
::* HV scan at fixed amplitude
 +
 
 +
* Planning to write report on all measurements and post in Wiki

Revision as of 12:04, 5 January 2018

SUBSYSTEM UPDATES

MAGNET (Bogdan)

  • Magnet main coil on the way from New Zealand - anticipated arrival at end of January
  • Magnet yoke on schedule for delivery end of January or beginning of February
  • Many parts are finished and will be going for painting. Still have to finish machine a few items, mostly the parts from the sawed plates. They are all ground and are not expected to take long to machine. A few of the rough machined items are out for heat treat. The painting is delayed because of the extreme cold right now.
  • Pictures of the yoke parts: Pic1, Pic2, Pic3
  • same dimensions, just in a different location


HV DIVIDERS (Julie)

  • Order was placed for 1200 dividers, anticipate 30 day delivery, assembly of a few hundred could be done by summer
  • Need sockets for full assembly
  • currently have ~200 PMTs and sockets at JLab (some have been machined from larger size, but all should be ok)
  • option to procure all sockets this year to finalize full assemblies by next year fall


FRAME (Carlos)

  • Planning to present design options at the collaboration meeting and to discuss possible optimizations. IPNO engineer/designer will also meet with Mike Fowler.


CRYSTALS (Carlos, Rong, Vladimir, TH)

  • Granite table ready for dimension measurements at JLab
  • IPNO setting up for crystal characterization measurements, carried out tests at Giessen U. for inter-laboratory comparison - data analysis ongoing
  • Microscopy and chemical composition analysis were carried out for 12 crystals at CUA.
  • chemical composition determined with XRF, statistical analysis suggests that both, stoichiometry and addition of other elements have an impact on optical properties, more detailed analysis ongoing
  • Optical measurements continuing at CUA


PMTs (Vladimir, A. Somov)

  • PMT characterization setup at JLab - fixed light leaks of dark box in the process
  • 65 PMTs were tested, all with the same divider
  • HV scan, measured amplitudes - looks good at first glance
  • HV scan at fixed amplitude
  • Planning to write report on all measurements and post in Wiki