(Created page with "Discussion items: * Magnet design and tests * Status of tungsten and lead blocks * TCS updates * Other PARTICIPANTS: Steven Lassiter, Dondal Day, Bogdan Wijtsekhowski, E...")
 
 
Line 5: Line 5:
 
* Status of tungsten and lead blocks
 
* Status of tungsten and lead blocks
  
* TCS updates
+
* TCS updates [https://wiki.jlab.org/cuawiki/images/4/41/Tcs_vertex_recon_dec_21.pdf link]
  
 
* Other
 
* Other
Line 14: Line 14:
  
 
'''MAGNET DESIGN AND TESTING
 
'''MAGNET DESIGN AND TESTING
'''
+
'''  
 
* In model added heating elements on top to reach larger temperature range for testing and evaluated  
 
* In model added heating elements on top to reach larger temperature range for testing and evaluated  
  

Latest revision as of 17:40, 3 December 2021

Discussion items:

  • Magnet design and tests
  • Status of tungsten and lead blocks
  • Other


PARTICIPANTS: Steven Lassiter, Dondal Day, Bogdan Wijtsekhowski, Erik Wrightson, Hamlet Mkrtchyan, Tanja Horn, Marie Boer, Rolf Ent, Vardan Tadevosyan


MAGNET DESIGN AND TESTING

  • In model added heating elements on top to reach larger temperature range for testing and evaluated
  • Copper brazing concept design
  • Temperature profile with two 1.2 kW heaters Tmax=893degC, Tabs=221 degC
  • still evaluating stresses, displacements, etc.
  • Temperature profile for two 2kW heaters
  • Heater element would have melted Tmax=1460degC (Copper meltung point 1085 degC), temperature along top absorber is 330degC
  • stresses, displacements look fine
  • Validating Fluent model with by-hand calculations
  • water flow, pressure, etc.
  • key for moving forward
  • Global timeframe towards magnet design
  • need global review of the magnet (resistor, fluid dynamics)
  • anticipate to start bidding in a few months
  • when magnet designed can start designing insert etc.
  • also want to do tests to see how much power can really withstand, etc.


TUNGSTEN BLOCKS

  • first delivery expected in January

LEAD BLOCKS

  • expect 7-8 tons, but not yet received

HALLD

  • At some point share CPS design with HallD engineering team - note that HallD needs 60kW but magnet can be longer
  • HallA/C: compact design since close to target
  • HallD: in tagger area - more space


TCS UPDATES (Vardan)


NEXT MEETING: FRIDAY JANUARY 14TH, 2022 AT 8AM ET