PARTICIPANTS: Bogdan, Carlos, Steven L., Vladimir, Fernando, Paulo, Hamlet, Brad, Vardan, Tanja, Hakob, Tristan, Marie, Rolf, Alexandre
PMT HV DIVIDER UPDATES
- Evaluation of noise level for new divider without shielding and with shielded box
- HV=605V @ 405uA, amplitude 10% of max
- noise unshielded: <110mVp-p (peak to peak)
- noise shielded: <5mVp-p (peak to peak)
- Tests with and without extra GND to clean GND
- Note: ADC 12bit/1V scale --> noise normal operations is ~1mV-2mV. Then for 5 mV peak to peak the RMS is ~< 2mV within the ADC noise
- For experiment have the threshold at ~30 MeV - 1% of 1V signal is 100mV, noise level seems acceptable
- also not triggering on pulse but need to collect amplitude
- Procurements have been submitted - expect dividers to be ready late March/early April
NPS ASSEMBLY
- Component testing space is available (EEL 126 and NPS Cleanroom)
- check with Vladimir/Brad on details of availability
- Final NPS assembly space is scheduled to be available on 4/28, but delays may be expected - a status update will be requested in February 2022
- may assume that part of the space will be available by mid-May for stacking blocks etc., even if no DAQ yet
- Travel plans for NPS assembly earliest in May 2022 - please note any feedback received from the February 2022 update
- Storage space in EEL126/NPS Cleanroom
- Shelves for crystals are being ordered
- Vladimir will follow up with Brad on getting a cabinet for storing the preshaped reflector foils
- Action items:
- Redo NPS assembly plan taking into account space availability
- Check with Facilities on progress with NPS assembly space
- Cabinet for pre-shaped foils in EEL 126
- Preshaped foils - follow up with Charles on those made at ODU in January
NEXT MEETING: THURSDAY 13 JANUARY AT 9AM ET
NPS PLANNING MEETING: THURSDAY 17 FEBRUARY AT 9AM ET (~3-4 hours)