General EEEMCal Meeting Summary 10/18/24
Jump to navigation
Jump to search
Back to Meeting Main Page --> Meeting Main
PARTICIPANTS: Renee, Richard, Carlos, Julien, Tanja, Douglas, Casey, Josh, Ioana, Gerard, Justin, Julie, Holly, Joerg, Hamlet, Vardan, Hrachya, Ethan, Irina,
NSF PROPOSAL
- UKY, JMU, W&M, MIT have submitted or are close to submitting their final budgets and other required documents to their SPO
- budgets have changed but overall we are within the required max limit
- spectrophotometer now comes with a dedicated computer and software - should argue that this is part of the equipment since it does not work without it
- OU, Lehigh, ACU, FIU have started preparing the documents and finalizing the budgets
- some discussions between all institutions on the budgets on going
- FIU encountered an issue with accessing the pre-proposal in Research.gov. Working on resolving it
- All required documents should be submitted to the CUA SPO by 4 November
- For narrative overleaf links and review/writing assignments see email
DESY BEAM TEST PREPARATIONS
- MIT equipment has arrived at DESY - everything is set to go for the 5x5 prototype
- The two SiPM channels for the MIT prototype are ready
- Josh/Larry have been testing the modules - two are ready, one is still being checked
- Action: send waveforms to the group when ready
- Status of the online diagnostics for the MIT prototype and also Crytur: see email by Casey Morean
- IJCLab-Orsay prototype has been experiencing delays but still expect to be ready for the beam test
- boards are scheduled to arrive early next week, which should leave time for testing and shipping to DESY
- The IJCLab-Orsay prototype will not have the fADC/discrete readout option for the beam test, but Gerard will try to evaluate some of the modules on the test bench
- working with Justin/Larry to get these boards manufactured
- Crytur prototype is ready
- Action: circulate the readout electronics scheme to the group
- The next call for proposals for the 2025 Spring test beam is out
- will discuss during/after test beam if we submit an application
EPIC PRE-TDR DISCUSSION
- Expect comments in the next few weeks
- Next deadline is 1 December
- need to fill in some project management related sections for that draft
EIC PROJECT
- Review for CD3B is ongoing next week - for crystals this is relevant for some of the long lead procurements
- Crytur has received the communication for submitting quotes etc. for the FY25 crystal orders - in discussion with BNL about the details
DOE FOA ON EIC GENERIC R&D
- Seems to be a more formal continuation of the EIC R&D program. Deadline is on 14 November
NEXT MEETING: TENTATIVELY IN THE WEEK OF 28 OCTOBER - PLEASE CHECK EMAIL