- Introduction
- Discussion about PbWO4 crystal and PMT procurement for FY17
- Discussion about chemical analysis details and future tests
- Magnet status
- Discussion about NPS beam pipe design at small angles
- Discussion about upcoming procurement of yoke and corrector coil
- Next steps include: finish detector design, design support platform (mechanical/civil), layout of utilities, detector interference, assembly of magnet and fringe field mapping.
- Status on PbWO4 testing and readout
- Discussion about impact of doping on light yield and radiation resistance
- Discussion about radiation resistance studies, in particular dose rate measurement
- Discussion about interest of APD/SiPM based readout of PbWO4 for SOLID and EIC - should continue these studies, also perform test in anechoic chamber
- Photon sources
- Timelike Compton Scattering with Transverse Target