General Meeting Summary 1/4/18

From Cuawiki
Revision as of 12:44, 5 January 2018 by Hornt (talk | contribs) (Created page with "SUBSYSTEM UPDATES MAGNET (Bogdan) * Magnet main coil on the way from New Zealand - anticipated arrival at end of January * Magnet yoke on schedule for delivery end of Janua...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

SUBSYSTEM UPDATES

MAGNET (Bogdan)

  • Magnet main coil on the way from New Zealand - anticipated arrival at end of January
  • Magnet yoke on schedule for delivery end of January or beginning of February
  • Many parts are finished and will be going for painting. Still have to finish machine a few items, mostly the parts from the sawed plates. They are all ground and are not expected to take long to machine. A few of the rough machined items are out for heat treat. The painting is delayed because of the extreme cold right now.
  • Pictures of the yoke parts: Pic1, Pic2, Pic3
  • same dimensions, just in a different location as before