General Meeting Summary 2/9/17

From Cuawiki
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

NPS MAGNET COMPONENT PROCUREMENT

  • Main coil awarded to Buckley
  • Discussion about yoke procurement
  • Multiple quotes available, the lowest are from Buckley and Standard Machine (not a standard magnet building company, which may have an impact on cost and scheduling)
  • Action item: check procedures at ODU
  • Corrector coil procurement can start as soon as final numbers are available


HIPS2017 RE-CAP

  • Good discussions and feedback on KL science case
  • Good progress with photon source designs - will have a follow-up meeting in next few weeks to converge on parameters


NPS ACTION ITEMS 2017

  • Frame design
  • priority is on finalizing design of light monitoring, curing, temperature control systems
  • Magnet
  • Discussion about relaxing timeline to plan to map NPS magnet to confirm fringe field estimates
  • Action item: update phrasing in document
  • Cabling, DAQ, electronics
  • Currently, cabling layout to detector frame assumes the same configuration as used in HyCal, need to check the details (connectors etc)
  • Action item: get drawings from Hycal to check connectors and see how cables go to patch, if choose different connectors, then need to evaluate (also in context of frame design)
  • Action item: check with Brad Sawatsky on final cable drawings and layout of experimental hall
  • Crystals
  • Could be beneficial for both NPS and EIC R&D projects to expedite the write-up on quality assurance, required infrastructure and methods