Schedule: | Schedule: | ||
* 2022-02-25 Fri. - Test fully automated CDC HV control | * 2022-02-25 Fri. - Test fully automated CDC HV control | ||
+ | ** Notify Beni and Mark Stevens of intent to run test on Fri. throughout the day with low voltages (~20V-30V) | ||
+ | ** Modify control script to subtract 2100V from suggested setting before applying | ||
+ | ** Create cronjob under hdops account to run script every 5min. | ||
+ | ** Monitor system occasionally throughout the day so that it runs for 4-6hrs | ||
* 2022-03-01 Tue. - Start system | * 2022-03-01 Tue. - Start system | ||
− | * | + | ** Notify halld@jlab.org that the test is starting and provide contact info. |
+ | ** Verify control script no longer subtracts 2100V from suggested setting | ||
+ | ** Confirm CDC gas is flowing and bubbler is correct | ||
+ | ** Confirm CDC alcohol level is good | ||
+ | ** Confirm BCAL chiller is on | ||
+ | ** Turn on all CDC HV channels | ||
+ | ** Turn on all BCAL HV,LV channels | ||
+ | ** Start DAQ system and confirm that cosmic trigger rate is correct (~100Hz?) | ||
+ | *** TODO: Get correct DAQ configuration details from Sergey | ||
+ | ** Set cronjob under hdops account to run script every 2min. and watch for a few cycles | ||
+ | ** Check CDC occupancy in RootSpy | ||
+ | *** TODO: Confirm that the occupancy histogram will work with cosmic events | ||
+ | *** TODO: Add additional monitoring plots to RootSpy | ||
+ | ** If all seems to be functioning, reset the crontab to run the script once per hour | ||
+ | ** Make HDLOG logbook entry | ||
+ | ** Monitor progress regularly for 2 weeks. Start new runs if needed. | ||
* 2022-03-14 Mon. - End test | * 2022-03-14 Mon. - End test | ||
Revision as of 16:52, 18 February 2022
Objectives:
- Test drive the AIEC software
- Demonstrate that the CDC gain is stable
Schedule:
- 2022-02-25 Fri. - Test fully automated CDC HV control
- Notify Beni and Mark Stevens of intent to run test on Fri. throughout the day with low voltages (~20V-30V)
- Modify control script to subtract 2100V from suggested setting before applying
- Create cronjob under hdops account to run script every 5min.
- Monitor system occasionally throughout the day so that it runs for 4-6hrs
- 2022-03-01 Tue. - Start system
- Notify halld@jlab.org that the test is starting and provide contact info.
- Verify control script no longer subtracts 2100V from suggested setting
- Confirm CDC gas is flowing and bubbler is correct
- Confirm CDC alcohol level is good
- Confirm BCAL chiller is on
- Turn on all CDC HV channels
- Turn on all BCAL HV,LV channels
- Start DAQ system and confirm that cosmic trigger rate is correct (~100Hz?)
- TODO: Get correct DAQ configuration details from Sergey
- Set cronjob under hdops account to run script every 2min. and watch for a few cycles
- Check CDC occupancy in RootSpy
- TODO: Confirm that the occupancy histogram will work with cosmic events
- TODO: Add additional monitoring plots to RootSpy
- If all seems to be functioning, reset the crontab to run the script once per hour
- Make HDLOG logbook entry
- Monitor progress regularly for 2 weeks. Start new runs if needed.
- 2022-03-14 Mon. - End test
Strategy:
- Designate 2130V as the nominal HV for cosmics, to raise more hits above the noise, but keep 20V headroom for the AI.
- Tell the AI that the HVB current is constant at 9uA so that it can operate within the range of its trained data
- Use 1V steps and 1h runs
- Starting new run every hour for 2 weeks may not be feasible. Devise scheme to break up long runs?
Needs:
- AIEC software to read epics and wait for a stable period before calculating the gain and setting the HV
- What determines "stable"?
- Who?
- Method for scaling the HVB current to what it would be at the nominal HV before running the AI - will not be needed for cosmics but will be needed for CPP.
- Is this something that could be tested during cosmics run? (yes=implement, no=defer)
- Script to project dE/dx for 4-10 GeV tracks, fit it and calculate the gain factor
- Is this for needed for cosmics? (monitoring?)
Code to set whole quadrants to same value(cdc_tool.py)
Questions:
Do we need to force a B field in the reconstruction sw (wait for Simon to answer)- Simon reported progress on straight track reconstruction (email to David and Naomi Feb. 24th)
Full DAQ or standalone DAQ?- Ask Sergey for configuration with only CDC, BCAL
When are we doing this?- March 1-14, 2022