(Created page with "The meeting time is 2:30pm. === Connection Info: === <div class="toccolours mw-collapsible mw-collapsed"> You can connect using [https://teams.microsoft.com/l/meetup-join/19%...") |
|||
Line 35: | Line 35: | ||
## RE input fifo 50% full as PID set-point for Schedule Density | ## RE input fifo 50% full as PID set-point for Schedule Density | ||
# [https://excalidraw.com/#room=66f0f7fbc2ca25f638bf,aYAB22Gl-Je5rngECJBLJQ Derek Howard (ESnet) to build CP for EJFAT and Perlmutter at NERSC with JLab assisting] | # [https://excalidraw.com/#room=66f0f7fbc2ca25f638bf,aYAB22Gl-Je5rngECJBLJQ Derek Howard (ESnet) to build CP for EJFAT and Perlmutter at NERSC with JLab assisting] | ||
− | ## CP [https://itnext.io/streaming-data-with-grpc-2eb983fdee11 gRPC] i/f to RE PID: Non-streaming / Peer-to-Peer ([https://grpc.io/blog/pubsub/ Note on gRPC Publish/Subscribe]) | + | ## Week of 2/6: Other ESnet projects |
− | ## [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/CP_PID_Sched.pdf?csf=1&web=1&e=JpffJ4 CP PID signal -> LB Schedule Density transform (Draft C++ algorithm '''completed''')] | + | ## Week of 2/13: |
− | ## [https://jeffersonlab.sharepoint.com/:p:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/ControlPlane.pptx?d=w005fee6e3a464b38aefcb1939b585d8a&csf=1&web=1&e=2tzZgJ Proposed Changes to RE Meta-Data] | + | ### Finish mock API server |
− | ## [https://github.com/esnet/esnet-smartnic-fw CP gRPC i/f to LB ('''pending''')] | + | ### create an internal representation of the load balancer calendar |
+ | ### implement the algorithm specified in [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/CP_PID_Sched.pdf?csf=1&web=1&e=JpffJ4 "EJFAT Load Balancer Schedule Density from Reassembly Engine PID control"] | ||
+ | ## Week of 2/20: Other ESnet projects | ||
+ | ## Week of 2/27: Add integration for the SmartNIC P4 Controller, synchronizing the internal state of the gRPC server with the P4 tables. | ||
+ | ## Week of 3/6: Other ESnet projects | ||
+ | ## Week of 3/13: Start work on integration test tooling. | ||
+ | ## Resources: | ||
+ | ### CP [https://itnext.io/streaming-data-with-grpc-2eb983fdee11 gRPC] i/f to RE PID: Non-streaming / Peer-to-Peer ([https://grpc.io/blog/pubsub/ Note on gRPC Publish/Subscribe]) | ||
+ | ### [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/CP_PID_Sched.pdf?csf=1&web=1&e=JpffJ4 CP PID signal -> LB Schedule Density transform (Draft C++ algorithm '''completed''')] | ||
+ | ### [https://jeffersonlab.sharepoint.com/:p:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/ControlPlane.pptx?d=w005fee6e3a464b38aefcb1939b585d8a&csf=1&web=1&e=2tzZgJ Proposed Changes to RE Meta-Data] | ||
+ | ### [https://github.com/esnet/esnet-smartnic-fw CP gRPC i/f to LB ('''pending''')] | ||
# [[EJFAT Status | Status]] | # [[EJFAT Status | Status]] | ||
# AOT | # AOT | ||
<hr> | <hr> |
Revision as of 13:37, 8 February 2023
The meeting time is 2:30pm.
Connection Info:
You can connect using Teams Link. (Click "Expand" to the right for details -->):
Agenda:
- Previous meeting
- Announcements:
- NERSC-ESnet-JLab on-site workshop Jan 31 - Feb 1
- Manuscript ESnet / JLab FPGA Accelerated Transport (No. TNS-00484-2022.R1) FINAL version submitted for publication to IEEE Transactions on Nuclear Science (TNS).
- Current Test set-up:
- CLAS12 files -> Carl C++ Packetizer -> LB -> Carls's C++ Reassembler -> ERSAP
- New Test set-up (pending):
- CLAS12 files -> Carl C++ Packetizer -> new LB (delivered) / dynamic CP (in progress) -> Carls's C++ Reassembler -> PID controller (completed) -> ERSAP
- RE input fifo 50% full as PID set-point for Schedule Density
- Derek Howard (ESnet) to build CP for EJFAT and Perlmutter at NERSC with JLab assisting
- Week of 2/6: Other ESnet projects
- Week of 2/13:
- Finish mock API server
- create an internal representation of the load balancer calendar
- implement the algorithm specified in "EJFAT Load Balancer Schedule Density from Reassembly Engine PID control"
- Week of 2/20: Other ESnet projects
- Week of 2/27: Add integration for the SmartNIC P4 Controller, synchronizing the internal state of the gRPC server with the P4 tables.
- Week of 3/6: Other ESnet projects
- Week of 3/13: Start work on integration test tooling.
- Resources:
- CP gRPC i/f to RE PID: Non-streaming / Peer-to-Peer (Note on gRPC Publish/Subscribe)
- CP PID signal -> LB Schedule Density transform (Draft C++ algorithm completed)
- Proposed Changes to RE Meta-Data
- CP gRPC i/f to LB (pending)
- Status
- AOT