Difference between revisions of "EJFAT EPSCI Meeting Jun. 21, 2023"
Jump to navigation
Jump to search
m (→Agenda:) |
m (→Agenda:) |
||
Line 62: | Line 62: | ||
# [https://ieeexplore.ieee.org/document/10046405 RT2022 Paper]: Submission Process Complete | # [https://ieeexplore.ieee.org/document/10046405 RT2022 Paper]: Submission Process Complete | ||
# [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/EJFAT_ACAT_2022_QL_sub.pdf?csf=1&web=1&e=dR566P ACAT2022 Paper]: - submitted | # [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/EJFAT_ACAT_2022_QL_sub.pdf?csf=1&web=1&e=dR566P ACAT2022 Paper]: - submitted | ||
− | # CHEP 2023 Conference Publication - '''in progress''' | + | # CHEP 2023 Conference Publication - '''in progress''' - deadline September 8, 2023 |
# Simulation | # Simulation | ||
## [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/pid-ql-rpt.pdf?csf=1&web=1&e=tZub0Z Use FIFO Levels] | ## [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/pid-ql-rpt.pdf?csf=1&web=1&e=tZub0Z Use FIFO Levels] |
Latest revision as of 19:08, 21 June 2023
The meeting time is 2:30pm.
Connection Info:
You can connect using Teams Link. (Click "Expand" to the right for details -->):
Agenda:
- Previous meeting
- Announcements:
Computer center power outage 06/20/2023Rescheduled
- NERSC Test Development:
- Data Source:
- JLAB, CLAS12, pre-triggered events - 1 channel
- Front End Packetizer pending mods for Tick-sync msg to CP - UDP packet to port on CP Host
- Derek Howard (ESnet) to build CP for EJFAT and Perlmutter at NERSC with JLab assisting
- Week of 6/18: Derek out through 6/21
- Local Installation of ESnet CP - in progress - requires new FPGA f/w (in progress)
- Data Sink:
- Perlmutter
- ERSAP
- Networking for Test
L3VPN Design with ESNetVet the cybersecurity controls with the security group.Implement Local network configuration changes/cybersecurity controls- Configure L3VPN, establish peering next
- Relocate to HACS-4 - soon
- Configure hosts to use tunnel, confirm traffic flow is as expected - last
- JLab Preliminary NERSC Test
- Test Plans - JLab, ESnet, NERSC:
- Data Source:
- Hall B CLAS12 detector streaming test - expecting to meet with Sergey B., D. Abbott on Thursday
- Issues for Thursday meeting:
- Number of streams
- Bandwidth per stream
- Test mode for VTP and/or real data. (Real data here may mean ready from detectors, but thresholds set low so as to trigger on noise).
- Bandwidth from Hall to Counting House
- Bandwidth from counting house to compute center.
- Status of Hall-B U280 order - will EPSCI need to supply one?
- Switch 7050 is expected to arrive some time around October; we have already transceivers, short cables and patch panel to connect up to 32 VTPs to it using two 10GBit links per VTP
- Fiber installation between hallb forward carriage and hallb counting room should be done this summer, will be enough for 24 VTPs using two 10GBit links per VTP
- We have only one fiber between hallb counting room and counting house second floor available right now, will order more fibers installation, may take several months
- There are several available fibers between counting house second floor and computer center (like 6), we can use a couple of them for our test
- Summary: sometime in October, we should have 48 10GBit links from 24 VTPs connected to the switch in hallb counting room, with that switch connected to computer center by 2x100GBit links
- Issues for Thursday meeting:
- RT2022 Paper: Submission Process Complete
- ACAT2022 Paper: - submitted
- CHEP 2023 Conference Publication - in progress - deadline September 8, 2023
- Simulation
- Demo Ready EJFAT Instance
- EJFAT Operational Status Board -> Prometheus Reporting
- Resources:
- AOT