Difference between revisions of "EJFAT EPSCI Meeting Feb. 15, 2023"

From epsciwiki
Jump to navigation Jump to search
(Created page with "The meeting time is 2:30pm. === Connection Info: === <div class="toccolours mw-collapsible mw-collapsed"> You can connect using [https://teams.microsoft.com/l/meetup-join/19%...")
 
 
Line 33: Line 33:
 
### '''Week of 2/13''':   
 
### '''Week of 2/13''':   
 
#### Finish mock API server
 
#### Finish mock API server
#### create an internal representation of the load balancer calendar
+
#### Create an internal representation of the load balancer calendar
#### implement the algorithm specified in [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/CP_PID_Sched.pdf?csf=1&web=1&e=JpffJ4 "EJFAT Load Balancer Schedule Density from Reassembly Engine PID control"]
+
#### Implement the algorithm specified in [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/CP_PID_Sched.pdf?csf=1&web=1&e=JpffJ4 "EJFAT Load Balancer Schedule Density from Reassembly Engine PID control"]
 +
#### Meeting with Derek 4PM EST Thursday
 
### Week of 2/20: Other ESnet projects
 
### Week of 2/20: Other ESnet projects
 
### Week of 2/27: Add integration for the SmartNIC P4 Controller, synchronizing the internal state of the gRPC server with the P4 tables.
 
### Week of 2/27: Add integration for the SmartNIC P4 Controller, synchronizing the internal state of the gRPC server with the P4 tables.
Line 42: Line 43:
 
### Perlmutter
 
### Perlmutter
 
### ERSAP
 
### ERSAP
# ACAT2022 Paper due March 5, 2023
+
# RT2022 Paper: Wrapping up Legal details for publishing rights, etc.
 +
# ACAT2022 Paper: due March 5, 2023
 
# Resources:
 
# Resources:
 
## [https://jeffersonlab.sharepoint.com/sites/HPDF HPDF]
 
## [https://jeffersonlab.sharepoint.com/sites/HPDF HPDF]

Latest revision as of 15:28, 15 February 2023

The meeting time is 2:30pm.

Connection Info:


Agenda:

  1. Previous meeting
  2. Announcements:
  3. NERSC Test set-up:
    1. Data Source: JLAB, CLAS12, pre-event aggregated - 1 channel
    2. Derek Howard (ESnet) to build CP for EJFAT and Perlmutter at NERSC with JLab assisting
      1. Week of 2/13:
        1. Finish mock API server
        2. Create an internal representation of the load balancer calendar
        3. Implement the algorithm specified in "EJFAT Load Balancer Schedule Density from Reassembly Engine PID control"
        4. Meeting with Derek 4PM EST Thursday
      2. Week of 2/20: Other ESnet projects
      3. Week of 2/27: Add integration for the SmartNIC P4 Controller, synchronizing the internal state of the gRPC server with the P4 tables.
      4. Week of 3/6: Other ESnet projects
      5. Week of 3/13: Start work on integration test tooling.
    3. Data Sink:
      1. Perlmutter
      2. ERSAP
  4. RT2022 Paper: Wrapping up Legal details for publishing rights, etc.
  5. ACAT2022 Paper: due March 5, 2023
  6. Resources:
    1. HPDF
    2. CP gRPC i/f to RE PID: Non-streaming / Peer-to-Peer (Note on gRPC Publish/Subscribe)
    3. CP PID signal -> LB Schedule Density transform (Draft C++ algorithm completed)
    4. Proposed Changes to RE Meta-Data
    5. CP gRPC i/f to LB (pending)
  7. Status
  8. AOT