(Created page with "The meeting time is 2:30pm. === Connection Info: === <div class="toccolours mw-collapsible mw-collapsed"> You can connect using [https://teams.microsoft.com/l/meetup-join/19%...") |
m (→Agenda:) |
||
Line 48: | Line 48: | ||
## Test Plan | ## Test Plan | ||
# [https://ieeexplore.ieee.org/document/10046405 RT2022 Paper]: '''Submission Process Complete''' | # [https://ieeexplore.ieee.org/document/10046405 RT2022 Paper]: '''Submission Process Complete''' | ||
− | # ACAT2022 Paper: '''due March | + | # ACAT2022 Paper: '''due March 19, 2023''' |
## writing up RL LB strategy/simulated results | ## writing up RL LB strategy/simulated results | ||
## '''Simulation Results may bear fruit for NERSC Test''' | ## '''Simulation Results may bear fruit for NERSC Test''' | ||
# AOT | # AOT | ||
<hr> | <hr> |
Latest revision as of 17:07, 8 March 2023
The meeting time is 2:30pm.
Connection Info:
You can connect using Teams Link. (Click "Expand" to the right for details -->):
Agenda:
- Previous meeting
- Announcements:
- NERSC Test Development:
- Data Source:
- JLAB, CLAS12, pre-event aggregated - 1 channel
- Front End Packetizer pending mods for Tick-sync msg to CP
- Derek Howard (ESnet) to build CP for EJFAT and Perlmutter at NERSC with JLab assisting
- Week of 2/13:
- Finish mock API server
- Create an internal representation of the load balancer calendar
- Implement the algorithm specified in "EJFAT Load Balancer Schedule Density from Reassembly Engine PID control"
- Meeting with Derek 4PM EST Thursday
- Week of 2/20: Other ESnet projects
- Week of 2/27: Add integration for the SmartNIC P4 Controller, synchronizing the internal state of the gRPC server with the P4 tables.
- Week of 3/6: Other ESnet projects
- Week of 3/13: Start work on integration test tooling.
- Week of 2/13:
- Data Sink:
- Perlmutter
- ERSAP
- RE pending mods for dialog with CP
- Test Plan
- Data Source:
- RT2022 Paper: Submission Process Complete
- ACAT2022 Paper: due March 19, 2023
- writing up RL LB strategy/simulated results
- Simulation Results may bear fruit for NERSC Test
- AOT