Difference between revisions of "EJFAT EPSCI Meeting May. 24, 2023"
Jump to navigation
Jump to search
m (→Agenda:) |
|||
Line 53: | Line 53: | ||
# [https://ieeexplore.ieee.org/document/10046405 RT2022 Paper]: Submission Process Complete | # [https://ieeexplore.ieee.org/document/10046405 RT2022 Paper]: Submission Process Complete | ||
# [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/EJFAT_ACAT_2022_QL_sub.pdf?csf=1&web=1&e=dR566P ACAT2022 Paper]: - submitted | # [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/EJFAT_ACAT_2022_QL_sub.pdf?csf=1&web=1&e=dR566P ACAT2022 Paper]: - submitted | ||
− | # ''' | + | # '''Simulation''' |
## [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/pid-ql-rpt.pdf?csf=1&web=1&e=tZub0Z Use FIFO Levels] | ## [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/pid-ql-rpt.pdf?csf=1&web=1&e=tZub0Z Use FIFO Levels] | ||
## [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/pid-ql-rpt-x.0.pdf?csf=1&web=1&e=IbXIdg Use EPR] | ## [https://jeffersonlab.sharepoint.com/:b:/r/sites/SciComp/Shared%20Documents/EPSCI/EJFAT/pid-ql-rpt-x.0.pdf?csf=1&web=1&e=IbXIdg Use EPR] |
Latest revision as of 17:22, 31 May 2023
The meeting time is 2:30pm.
Connection Info:
You can connect using Teams Link. (Click "Expand" to the right for details -->):
Agenda:
- Previous meeting
- Announcements:
- NERSC Test Development:
- Data Source:
- JLAB, CLAS12, pre-triggered events - 1 channel
- Front End Packetizer pending mods for Tick-sync msg to CP - UDP packet to port on CP Host
- Derek Howard (ESnet) to build CP for EJFAT and Perlmutter at NERSC with JLab assisting - ETA + 2 weeks?
- Week of 5/21: CP Development
- Data Sink:
- Perlmutter
- ERSAP
- Networking for Test - ETA + 2 weeks?
- L3VPN Design with ESNet (done)
- Configure L3VPN, establish peering (in progress)
- Vet the cybersecurity controls with the security group. (in progress)
- Relocate to HACS-4
- Configure hosts to use tunnel, confirm traffic flow is as expected
- Implement Local network configuration changes/cybersecurity controls
- Test Plans - JLab, ESnet, NERSC:
- JLab Preliminary NERSC Test
- Data Source:
- Hall B CLAS12 detector streaming test
- Switch 7050 is expected to arrive some time around October; we have already transceivers, short cables and patch panel to connect up to 32 VTPs to it using two 10GBit links per VTP
- Fiber installation between hallb forward carriage and hallb counting room should be done this summer, will be enough for 24 VTPs using two 10GBit links per VTP
- We have only one fiber between hallb counting room and counting house second floor available right now, will order more fibers installation, may take several months
- There are several available fibers between counting house second floor and computer center (like 6), we can use a couple of them for our test
- Summary: sometime in October, we should have 48 10GBit links from 24 VTPs connected to the switch in hallb counting room, with that switch connected to computer center by 2x100GBit links
- RT2022 Paper: Submission Process Complete
- ACAT2022 Paper: - submitted
- Simulation
- Demo Ready EJFAT Instance
- EJFAT Operational Status Board -> Prometheus Reporting
- Resources:
- AOT