Meeting URL https://bluejeans.com/253300597?src=join_info Meeting ID 253 300 597 Want to dial in from a phone? Dial one of the following numbers: +1.888.240.2560 (US Toll Free) (see all numbers - https://www.bluejeans.com/premium-numbers) Enter the meeting ID and passcode followed by # Connecting from a room system? Dial: bjn.vc or 199.48.152.152 and enter your meeting ID & passcode
Agenda:
- Previous meeting
- Announcements
- Streaming Data Scientist position
- SRO Workshop VII (zoom),(homepage) (indico)
- SRO meeting cancelled this afternoon due to workshop
- Fortnight paper for Mon. 11/23:
- Ongoing Activities
- JLab Common Environment (CE) + SPACK (Thomas, Nathan)
- EVIO-6 (Carl)
- JANA2 (Nathan)
- GlueX port
- ACTS + EIC
- A.I.
- JLab AI webpage (Kishan)
- Hydra (Kishan/Thomas)
- A.I.I.
- Experimental Controls (David)
- CODA/DAQ Software Support
- CLARA Support
- SRO (Vardan)
- Hall-B/D TriDAS
- ERSAP
- Offsite Computing
- BigRed3 at IU (David)
- NERSC (David)
- OSG (Thomas)
- GUI for Calorimeter calibration scripts (Hall-D Request) (Thomas)
- Publications
- AOT
Minutes:
Attendees: David L., Carl T., Nathan B., Kishan R., Vardan G., Thomas B.
Previous Meeting
- SoLID
- Carl reached out to Zhiwen who responded that they would be having a simulation meeting, but no general software meeting. No other info given.
- DAQ system for SoLID will be different than others at JLab and will likely require our input. Carl will look into who is designing that.
Announcements
- Streaming Readout Workshop VII is happening this week. EPSCI SRO meeting for this afternoon cancelled
SPACK
- Nathan contacted Thomas, but not much movement yet
- David will see about helping.
EVIO-6
- Difficult part of documentation is done.
- Dave A. requested C-API be maintained as is.
- Carl will look at this and make sure documentation and source is updated where needed. Not expected to be a significant amount of work.
JANA2
- GlueX Port progressing. Some issues with factory calls that seem to be unresolved, causing stop conditions. Working trough them.
- ACTS + EIC
- Met with EIC group last week and Nathan updated on current work.
- Path is clear on what is needed next.
- Agreed to meet again in ~3 weeks
AI
- Kishan posted another page on SciComp to describe installing custom kernels for Jupyter. Still a few things to finalize, but mostly there.
- Some new updates posted to JLab AI pages for review (David needs to approve)
- Hydra
- Code jam week before last successful
- The major refactoring of the hydra code is largely done and the system was running
- Some issue with web page updating, but not considered a major problem and should be easily fixed
- Experimental Controls: Two positions entered into Peoplefluent but have not yet been approved
CLARA Support
- Some confusion on how conflicts with parameter names in global and local levels are handled. Some options discussed with Hall-B and it was decided the priorities in the existing code should be left.
SRO
- Indra lab test setup
- Ben R. and Dave A. solved issue with Indra test setup where no hits were being seen in Vardan's testing the previous week
- Currently VTP test setup provides 300MByte/sec/link data rate.
- Able to get 1% deadtime fairly quickly with multiple threads. For 600MByte/sec aggregated (2 VTP streams) stream processing 2.5 cores are used for aggregation and 4 cores are used for hit finder.
- 1% dead time that was also present during the beam test was due to the disruptor ring-buffer tuning. Problem solved, but expected to be optimized again for the large data volumes (will see). in coming week/s an additional splitter will be installed to provide ~900MByte/s/link.
- Aggregate rate of ~600MB/s with no loss of the VTP frames was achieved.
- TriDAS
- Sergey B. presented estimation of data rates at HAll-B SRO meeting last week.
- Suggested the current design spec should be for 5GB/s streams with the ability to scale to multiple 5GB/s streams
Offsite
- Production running still at NERSC, PSC, IU. Documentation still needed for new NERSC and IU workflows so it can be handed over to Hall-D postdoc
- OSG sent first jobs into JLab
- Jobs started but had issues running
- May well have fully running jobs by end of week (depends on vacation schedule of key OSG personnel)
Publications
- Everyone was encouraged to add their most recent publications (including proceedings) to the EPSCI publications page so we can fill in the blank section of the home page.