Difference between revisions of "The HPS Run Wiki"
Jump to navigation
Jump to search
Line 123: | Line 123: | ||
* After MCC finishes beam tune | * After MCC finishes beam tune | ||
** make sure beam conditions did not changed, beam position and halo counter rates are as before (see logbook from previous days) | ** make sure beam conditions did not changed, beam position and halo counter rates are as before (see logbook from previous days) | ||
+ | ** work with MCC to move bean position and direction to see if lower counts on upstream halo counters can be achieved (UPS-L and UPS-R) | ||
+ | <b> Upstream halo counters must count <10Hz, downstream counters ~Hz </b> | ||
− | |||
− | |||
− | |||
** perform harp scans to verify that beam profile did not changed (2C21 and tagger/2C24 harps), Use UPS-L for analysis, send harp scan results to the logbook | ** perform harp scans to verify that beam profile did not changed (2C21 and tagger/2C24 harps), Use UPS-L for analysis, send harp scan results to the logbook | ||
* After beam tune is done send HPS scaler GUI to the logbook with proper comment | * After beam tune is done send HPS scaler GUI to the logbook with proper comment |
Revision as of 15:58, 17 March 2015
[edit]
Important Phone NumbersShift ScheduleChecklists |
Procedures |
Manuals |
JLab Logbooks
|
RC: Stepan Stepanyan
PDL: Harut AvagyanEvery Shift:
SVT InstructionsBefore sending beam to Faraday cup, verify (and page expert if otherwise):
The first time sending beam to the Faraday cup after the hall is closed, page the SVT expert. Every Run:
|
Run Plan:March 18-19 (morning)Always Setup Beam to the Hall-B Tagger Dump after long down
Upstream halo counters must count <10Hz, downstream counters ~Hz
Setup Beam to the Hall-B Faraday cup Dump and Setup HPS.
At 6am ask MCC for tagger magnet OFF and degaused, and hall swiped and put to the restricted access
|
|
|
|
|
|
|
|