Difference between revisions of "The HPS Run Wiki"
Line 140: | Line 140: | ||
* If everything looks normal, rates on downstream counters are <10Hz, and on HPS-L and HPS-R are <30Hz at 10nA, send main HPS scaler GUI to the logbook and proceed | * If everything looks normal, rates on downstream counters are <10Hz, and on HPS-L and HPS-R are <30Hz at 10nA, send main HPS scaler GUI to the logbook and proceed | ||
* Use 2H02A harp to measure beam profile (beam current should not exceed 20 nA), beam size should be X-width ~250 um Y-width < 50 um. Beam should be within ~1mm of recent measurements. | * Use 2H02A harp to measure beam profile (beam current should not exceed 20 nA), beam size should be X-width ~250 um Y-width < 50 um. Beam should be within ~1mm of recent measurements. | ||
− | * Record Ecal count rates top vs bottom. Beam centered? | + | * Record Ecal count rates top vs bottom. Beam centered vertically? |
− | * Turn beam off. Insert SVT Protection Collimator 4mm slit to its nominal position. Vertically scan the collimator, measuring the halo counter rates vs vertical position. Beam should be within ~1mm of center. | + | * Turn beam off. Insert SVT Protection Collimator 4mm slit to its nominal position. Ecal Backgrounds? Vertically scan the collimator, measuring the halo counter rates vs vertical position. Beam should be within ~1mm of center. |
'''<font size=3> Give beams to machine for BPM calibration asap in day shift. </font>''' | '''<font size=3> Give beams to machine for BPM calibration asap in day shift. </font>''' | ||
FIRST: must complete above to ensure beams are safely centered in SVT. If have extra time before day shift, | FIRST: must complete above to ensure beams are safely centered in SVT. If have extra time before day shift, | ||
− | proceed to chicane set up. | + | proceed to chicane set up below. |
'''<font size=3> Energize chicane.</font>''' | '''<font size=3> Energize chicane.</font>''' | ||
Line 153: | Line 153: | ||
* After magnets are at required settings (will take ~40 min) ask MCC for 10 nA beam | * After magnets are at required settings (will take ~40 min) ask MCC for 10 nA beam | ||
* Observe beam spot on chromax viewer, beam spot should be at the same place as before magnets were turned ON. If spot is shifted, change Frascati magnets curent to correct the position - if beam is left of the original point current must be lowered, if it is shifted right current must be increased. Do current change with small steps, ~1 Amp. | * Observe beam spot on chromax viewer, beam spot should be at the same place as before magnets were turned ON. If spot is shifted, change Frascati magnets curent to correct the position - if beam is left of the original point current must be lowered, if it is shifted right current must be increased. Do current change with small steps, ~1 Amp. | ||
− | <b>Be very careful when changing | + | |
+ | <b>Be very careful when changing magnet currents when beams are on. Must enter new current ACCURATELY. Small steps only. </b> | ||
+ | |||
* After chicane is set, record halo counter rates, turn beam off and insert HPS target, 4um W | * After chicane is set, record halo counter rates, turn beam off and insert HPS target, 4um W | ||
− | * Do horizontal scan of beam on target. Using table provided change | + | * Do horizontal scan of beam on target. Using table provided, first change Frascati settings, then PS settings to move beam left and right on the target with ~1mm step. Small changes only. |
− | * Center beam on target with appropriate chicane currents just determined. Record bpm and screen shot. | + | *Record halo counter rates and magnets currents. First move right, stop when rates on halo counters will increase by several times, then move left until rates will start to go up. |
+ | * Center beam on target with appropriate chicane currents just determined. Record bpm and screen shot and Ecal scalers. | ||
* Do vertical scan of beam. Measure Ecal rates top/bottom vs vertical beam position. Record bpm 2H02 y and Ecal rates. Move beam vertically on bpm using upstream correctors, by 0.5 mm steps. Don't exceed 2mm motion. | * Do vertical scan of beam. Measure Ecal rates top/bottom vs vertical beam position. Record bpm 2H02 y and Ecal rates. Move beam vertically on bpm using upstream correctors, by 0.5 mm steps. Don't exceed 2mm motion. | ||
Revision as of 16:25, 19 March 2015
Important Phone NumbersShift ScheduleChecklists |
Procedures |
Manuals |
JLab Logbooks
|
RC: John Jaros
PDL: Harut AvagyanEvery Shift:
SVT InstructionsBefore sending beam to Faraday cup, verify (and page expert if otherwise):
The first time sending beam to the Faraday cup after the hall is closed, page the SVT expert. Every Run:
|
Run Plan:March 19-20, 2015 (day/swing/owl)Overview: Machine will stop at noon for LCW heat exchanger replacement. No beam to Hall B before noon. Machine restarts ~5PM. So day shift is cancelled, but swing and owl shifts are on. Beams to Hall B scheduled for swing, so shift should go to controlled access in preparation and sweep hall when beams are imminent. Beams are expected mid-late swing. Program same as yesterday: 1) restore beams to tagger; (2)take beams to Hall B dump and install SVT Collimator; (3)starting Mar 20 day shift, make beams available to machine for BPM calibration; (5)set up chicane and test beam location on target Always Setup Beam to the Hall-B Tagger Dump after long down
Upstream halo counters must count <10Hz, downstream counters ~Hz
Setup Beam to the Hall-B Faraday cup Dump and Setup HPS.
Move beam with upstream correctors only This will guarantee small angles through HPS and safety of SVT
Beam should be centered using correctors on 2C21, 2C23, and 2C24 girder
Give beams to machine for BPM calibration asap in day shift. FIRST: must complete above to ensure beams are safely centered in SVT. If have extra time before day shift, proceed to chicane set up below. Energize chicane.
Be very careful when changing magnet currents when beams are on. Must enter new current ACCURATELY. Small steps only.
|
|
|
|
|
|
|
|
Webcams:
|
Slow Controls: |
Accelerator:
|
Offline: |