Difference between revisions of "July 28th, 2023"

From kl project
Jump to navigation Jump to search
Line 1: Line 1:
<b>Attended</b>: ''Moskov'', ...''Igor''.
+
<b>Attended</b>: ''Moskov'', ...''Igor''. ''Jim'' and ''Jeoff'' are traveling.
  
 
* On Aug 2nd, ERR-I is sceduled.  All details are in [https://wiki.jlab.org/klproject/index.php/KLF_Phase_I_ERR].
 
* On Aug 2nd, ERR-I is sceduled.  All details are in [https://wiki.jlab.org/klproject/index.php/KLF_Phase_I_ERR].

Revision as of 10:01, 26 July 2023

Attended: Moskov, ...Igor. Jim and Jeoff are traveling.

  • On Aug 2nd, ERR-I is sceduled. All details are in [1].


  • On July 25th, we had a Marco muBDX@KLF/CPS meeting disciss the following...
  • Tonino gave a short presentation about the work he did in the old configuration and the integration in the new.
  • We discussed:
    • Options to move upstream the whole CPS.
    • Options to deflect 0.5 GeV - 5 GeV muons on one side of the beamline:
    • Options to shield the detector set up:
      • 1) Increasing the permanent magnet Bdl or
      • 2) Switching from a pure permanent to a permanent/powerd magnet
      • 3) Adding a further magnet downstream.
    • Weight, available clearance, of the two dipoles necessary to determine incoming/scattered muon momentum.
    • Other possible issues.
    • Coordination with KLF Coll and Hall-D team.


  • On July 24th, we had a Hovanes CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [2].