Present:  Hovanes, Chris, Tim, Josh, Vitaly, Eugene, Beni, Edy, Richard, Marshall, Sean, Pavel
 
Present:  Hovanes, Chris, Tim, Josh, Vitaly, Eugene, Beni, Edy, Richard, Marshall, Sean, Pavel
 +
----
 +
 +
 +
Hovanes announced that KLF is at the stage where procurements with large amounts are going to be made soon. KLF leadership will need to carefully check the drawings of the beamline components as they become available to make sure that they satisfy the needs of the core physics program of the experiments. It is not necessary to check the mechanical stability, thermal aspects, or the radiation control issues assuming that they have been addressed by the experts.  The drawings will be posted by Tim or Hovanes as they become available well before Purchase Requests are submitted.
 +
 +
 
----
 
----

Revision as of 11:30, 12 July 2024

Agenda

  • Announcements
  • CPS simulation updates (Pavel)
  • Do we need photon beam in the hall during KLF? (Sean, Mikhail, Ig)
  • Any other business

Minutes

Present: Hovanes, Chris, Tim, Josh, Vitaly, Eugene, Beni, Edy, Richard, Marshall, Sean, Pavel



Hovanes announced that KLF is at the stage where procurements with large amounts are going to be made soon. KLF leadership will need to carefully check the drawings of the beamline components as they become available to make sure that they satisfy the needs of the core physics program of the experiments. It is not necessary to check the mechanical stability, thermal aspects, or the radiation control issues assuming that they have been addressed by the experts. The drawings will be posted by Tim or Hovanes as they become available well before Purchase Requests are submitted.