July 28th, 2023

From kl project
Revision as of 07:44, 26 July 2023 by Igor (talk | contribs)
Jump to navigation Jump to search

Attended: Moskov, ...Igor.

  • On Aug 2nd, ERR-I is sceduled. All details are in [1].


  • On July 25th, we had a Marco muBDX@KLF/CPS meeting disciss the following...
  • Tonino gave a short presentation about the work he did in the old configuration and the integration in the new.
  • We discussed:
    • Options to move upstream the whole CPS.
    • Options to deflect 0.5 GeV - 5 GeV muons on one side of the beamline:
    • Options to shield the detector set up:*** 1) Increasing the permanent magnet Bdl or
      • 2) Switching from a pure permanent to a permanent/powerd magnet
      • 3) Adding a further magnet downstream.
    • Weight, available clearance, of the two dipoles necessary to determine incoming/scattered muon momentum.
    • Other possible issues.
    • Coordination with KLF Coll and Hall-D team.


  • On July 24th, we had a Hovanes CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [2].