August 11th, 2023

From kl project
Revision as of 10:29, 7 August 2023 by Igor (talk | contribs)
Jump to navigation Jump to search

Attended: Moskov, ... Igor.

  • On August 7th, we had a Hovanes CPS meeting discuss CPS design for Hall D and to prepare for ERR-I [1].


  • David Hamilton informed us that the Hall C CPS report that we submitted to lab management to get the C1 condition on E12-17-008 lifted? In which case, the conceptual design report for the Hall C CPS is here (this is what we sent to Bob and was reviewed by Patrizia): [2]
  • The original experimental proposal is here: [3]. We were fully re-approved by PAC51 two weeks ago.


  • Tentive agenda for the KLF Collaboration meeting (September 19th [4]):
  • (10+5') Cynthia Keppel, [Welcome Remarks].
  • (20+10') Doug Higinbotham, [Summary for KLF ERR-I].
  • (15+5') Mikhail Bashkanov, [Excited Omega baryon states at KLF].
  • (15+5') Tim Whitlatch, [K-Long Engineering update].
  • (15+5') Mikhail Bashkanov, [The Flux Monitor - final design].
  • (15+5') Shukui Zhang, [Status of the CEBAF photo-injector drive laser system for KL beam].