Minutes from Wed. 10/11/2017 Scheduling meeting:

  • Clean room was moved to LERF vault 10/10/17
  • CM FL02 upstream end prepared for Vacuum work 10/12/17
  • Work on securing cryomodule vacuum will continue over the next weeks, followed by the move of the C20 from zone 4 to zone 2. This will then be re-connected to cryo & RF system
  • Kevin & Wes to visit SLAC 10/17-19/17
  • PSS certification scheduled for 10/30/17
  • Cryomodule move of FL02 & FL03 scheduled for 11/2/17
  • Cooldown of the LERF transferlines, the quarter & zone 2 will be after the CHL trip scheduled for week of November 12???


Cryomodule clean tent in place to secure Zone 2 vacuum