Remaining tasks for LCLS-II Cryomodule testing
 +
Kevin Jordan 7/26/2018
 +
System Task Group Responsible Notes
 +
Installation / Pipe fitting / Welding PRIOR to testing
 +
Transferline
 +
Confirm/Prep both transferline sections have proper weld prep Cryo
 +
Locate and affix to floor short piece Installation
 +
Locate and affix to floor  "L" piece Installation
 +
Position/align both sections with ruler and level bar Cryo
 +
Cut, prep, & weld field fit joints per weld spec - w/M. Martin advice Cryo
 +
Leak check innner connections prior to SI wrap Cryo/SRF?
 +
Cut/prep & weld clam shells Cryo
 +
 +
Warm Helium Piping
 +
Prep, mount, and weld sections of warm piping per spec & drawings Cryo Much of this is to be done after the cryo-can is located & grouted
 +
 +
Cryo-Can
 +
Remove/install equipment that is too tall for cable tray/waveguide Gubeli Ensure that it can be moved into place w/o hight restrictions like relief stack
 +
Confirm/Prep the weld joints have proper weld prep Cryo
 +
Locate Cryo-can per surveyed drill locations Installation
 +
Confirm alignment to field fit transferline Survey/Gubeli
 +
Drill, mount/level can, grout base plate Installation
 +
Cut to fit, weld & leak check inner Helium piping Cryo
 +
Wrap SI insulation Cryo/SRF
 +
Cut to fit & weld outer clam shells Cryo
 +
 +
Clean Room Assembly
 +
Unpack & assemble Electricians This can be done once the cryo-Can has been moved into place
 +
Install AC power and lights Electricians
 +
 +
 +
 +
 +
 +
  
== Transferline installation ==
+
=== Work to move, locate, and join 2 cryomodules prior to testing ===
*
+
*
 
*
 
  
== Cryo-Can Installation ==
+
== Movement ==
*
+
*
+
Bolt on wheels SRF Installation crew can assist if required
*
+
Arrange for crane at LERF to Lower/Raise CMs Installation
 
+
Move to/from Test Lab SRF
 
+
Wheel in/out LERF SFR/Installation
== Warm Helium Piping ==
+
Locate/position CMs SFR/Survey This will likely be done wioth plumb bobs
*
+
*
+
Cleanroom beam tube connection
*
+
Prepare & execute center beam tube connections in cleam room per procedures SRF/Vac This is the effort to join two modules together
 +
Insulate SRF
 +
 +
Cryo-Can & Center Bellows * these details are TBD *
 +
Affix the bellows to cart Installation (?) The cryo-can bellows may arrive on the end of the CM - TBD
 +
Position cryo-can bellows SRF The cart enables ease of installation in the joining region
 +
Secure cryo-can bellows SRF
 +
Position center bellows These connect the vacuum space of the two CMs together
 +
Secure center bellows
 +
 +
Cooldown
 +
Follow Mike Drury's proceedures

Revision as of 09:35, 27 July 2018

Remaining tasks for LCLS-II Cryomodule testing Kevin Jordan 7/26/2018 System Task Group Responsible Notes Installation / Pipe fitting / Welding PRIOR to testing Transferline Confirm/Prep both transferline sections have proper weld prep Cryo Locate and affix to floor short piece Installation Locate and affix to floor "L" piece Installation Position/align both sections with ruler and level bar Cryo Cut, prep, & weld field fit joints per weld spec - w/M. Martin advice Cryo Leak check innner connections prior to SI wrap Cryo/SRF? Cut/prep & weld clam shells Cryo

Warm Helium Piping Prep, mount, and weld sections of warm piping per spec & drawings Cryo Much of this is to be done after the cryo-can is located & grouted

Cryo-Can Remove/install equipment that is too tall for cable tray/waveguide Gubeli Ensure that it can be moved into place w/o hight restrictions like relief stack Confirm/Prep the weld joints have proper weld prep Cryo Locate Cryo-can per surveyed drill locations Installation Confirm alignment to field fit transferline Survey/Gubeli Drill, mount/level can, grout base plate Installation Cut to fit, weld & leak check inner Helium piping Cryo Wrap SI insulation Cryo/SRF Cut to fit & weld outer clam shells Cryo

Clean Room Assembly Unpack & assemble Electricians This can be done once the cryo-Can has been moved into place Install AC power and lights Electricians




Work to move, locate, and join 2 cryomodules prior to testing

Movement

Bolt on wheels SRF Installation crew can assist if required Arrange for crane at LERF to Lower/Raise CMs Installation Move to/from Test Lab SRF Wheel in/out LERF SFR/Installation Locate/position CMs SFR/Survey This will likely be done wioth plumb bobs

Cleanroom beam tube connection Prepare & execute center beam tube connections in cleam room per procedures SRF/Vac This is the effort to join two modules together Insulate SRF

Cryo-Can & Center Bellows * these details are TBD * Affix the bellows to cart Installation (?) The cryo-can bellows may arrive on the end of the CM - TBD Position cryo-can bellows SRF The cart enables ease of installation in the joining region Secure cryo-can bellows SRF Position center bellows These connect the vacuum space of the two CMs together Secure center bellows

Cooldown Follow Mike Drury's proceedures