Attendees: Curt Hovater, Dave Seidman, Mark Wissmann, Joe Gubeli, Kevin Jordan
 
Attendees: Curt Hovater, Dave Seidman, Mark Wissmann, Joe Gubeli, Kevin Jordan
Waveguide attenuation numbers were discussed - Curt will check Joe's
+
 
 +
Waveguide attenuation numbers were discussed - Curt will check Joe's attenuations against SLAC's numbers.
 +
 
 +
The field probe cables will be routed up through the penetration from the prior zone so that they do not have to "double back"
 +
 
 +
The cables will be routed along the floor and covered with a trough approved by safety
 +
 
 +
Dave will submit ATLis to do a test cable pull to determine actual length for the field probe heliax cable

Latest revision as of 11:45, 27 October 2017

Attendees: Curt Hovater, Dave Seidman, Mark Wissmann, Joe Gubeli, Kevin Jordan

Waveguide attenuation numbers were discussed - Curt will check Joe's attenuations against SLAC's numbers.

The field probe cables will be routed up through the penetration from the prior zone so that they do not have to "double back"

The cables will be routed along the floor and covered with a trough approved by safety

Dave will submit ATLis to do a test cable pull to determine actual length for the field probe heliax cable