(Created page with " Weekly Reporting LERF Conversion Week of October 26 – November 1, 2017 Issues: None yet LERF accomplishments this week: Safety Assessment document is in progress The 480...")
 
Line 4: Line 4:
 
Week of October 26 – November 1, 2017
 
Week of October 26 – November 1, 2017
  
Issues:   
+
== Issues: ==  
 
None yet
 
None yet
LERF accomplishments this week:
+
== LERF accomplishments this week: ==
 
Safety Assessment document is in progress
 
Safety Assessment document is in progress
 +
 
The 480 VAC panel work for the SSA power is in progress
 
The 480 VAC panel work for the SSA power is in progress
 +
 
Network switches are on order
 
Network switches are on order
 +
 
All CEBAF modules and girder vacuums have been secured in preparation for removing girders and two modules as well as shuffling the third from zone 4 to zone 2
 
All CEBAF modules and girder vacuums have been secured in preparation for removing girders and two modules as well as shuffling the third from zone 4 to zone 2
 +
 
The two racks for network, servers, and vacuum controls have been moved into place in the gallery. Bases are on order then power can be connected. An ATLis has been submitted for connecting 120VAC power to SSAs and to the racks.
 
The two racks for network, servers, and vacuum controls have been moved into place in the gallery. Bases are on order then power can be connected. An ATLis has been submitted for connecting 120VAC power to SSAs and to the racks.
 +
 
LCLS-II CM #1 & #2 locations (including waveguide) have been taped out on the vault floor in preparation for cable order – both cryogenic control and RF/LLRF cables
 
LCLS-II CM #1 & #2 locations (including waveguide) have been taped out on the vault floor in preparation for cable order – both cryogenic control and RF/LLRF cables
Upcoming Activities:
+
 
 +
== Upcoming Activities: ==
 
Cryomodule shuffle and two cryomodule removal from vault
 
Cryomodule shuffle and two cryomodule removal from vault
 +
 
Completion of the Process & Instrumentation diagram for the cryogenic end can & transferline
 
Completion of the Process & Instrumentation diagram for the cryogenic end can & transferline
 +
 
Complete Safety Assessment document
 
Complete Safety Assessment document
 +
 
Cable procurement
 
Cable procurement
 +
 
Server procurement  
 
Server procurement  
  
Electrical panels for SSA power
 
  
Clean hood in place for CM vacuum work
+
 
 +
Layout of cryomodules in accelerator vault
 +
 
 +
Vacuum spaces secured for cryomodule shuffle

Revision as of 10:11, 1 November 2017

Weekly Reporting LERF Conversion Week of October 26 – November 1, 2017

Issues:

None yet

LERF accomplishments this week:

Safety Assessment document is in progress

The 480 VAC panel work for the SSA power is in progress

Network switches are on order

All CEBAF modules and girder vacuums have been secured in preparation for removing girders and two modules as well as shuffling the third from zone 4 to zone 2

The two racks for network, servers, and vacuum controls have been moved into place in the gallery. Bases are on order then power can be connected. An ATLis has been submitted for connecting 120VAC power to SSAs and to the racks.

LCLS-II CM #1 & #2 locations (including waveguide) have been taped out on the vault floor in preparation for cable order – both cryogenic control and RF/LLRF cables

Upcoming Activities:

Cryomodule shuffle and two cryomodule removal from vault

Completion of the Process & Instrumentation diagram for the cryogenic end can & transferline

Complete Safety Assessment document

Cable procurement

Server procurement


Layout of cryomodules in accelerator vault

Vacuum spaces secured for cryomodule shuffle