11/2/2017 - All of the girders have been removed in preparation of CM move & shuffle [[https://wiki.jlab.org/lerf/index.php/Girder_removal]] | 11/2/2017 - All of the girders have been removed in preparation of CM move & shuffle [[https://wiki.jlab.org/lerf/index.php/Girder_removal]] | ||
− | 11/1/2017 - Last of the cryomodule vacuums & girders have been secured & the clean room has been removed from the vault, the cryomodule & waveguide layout has been taped out on vault floor | + | 11/1/2017 - Last of the cryomodule vacuums & girders have been secured & the clean room has been removed from the vault, the cryomodule & waveguide layout has been taped out on vault floor [[https://wiki.jlab.org/lerf/index.php/File:Cm_tape.JPG]] |
10/31/2017 - Cable length & routing checks being made | 10/31/2017 - Cable length & routing checks being made |
Revision as of 09:04, 2 November 2017
11/2/2017 - All of the girders have been removed in preparation of CM move & shuffle [[1]]
11/1/2017 - Last of the cryomodule vacuums & girders have been secured & the clean room has been removed from the vault, the cryomodule & waveguide layout has been taped out on vault floor [[2]]
10/31/2017 - Cable length & routing checks being made
10/30/2017 - Network switches ordered, 2 racks moved to gallery, cryomodule vacuum isolation continues
10/27/2017 - 3 of the 6 vacuum connections for the CEBAF style cryomodules have been secured, had a cable planning meeting
10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process
10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault
10/24/2017 - 480 VAC panels are being mounted in gallery
10/11/2017 - Waveguide design review
10/10/2017 - Clean Hoods have been moved to vault
10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs