11/6/2017 - Draft P & ID drawing done & posted [[https://wiki.jlab.org/lerf/index.php/P&ID rev-draft.pdf]]
  
 
11/3/2017 - GW magnets were radcon surveyed and moved to storage in BLDG 36, 2 PCs were ordered for PLC programming of Cryo controls & vacuum controls, service request submitted to move rack from free stock to LERF gallery - this is a 36" deep rack for the servers (& free {;-), the network has been created for the project; lclsnet - [https://logbooks.jlab.org/entry/3491092], Active VVUs have been installed on 480 VAC panels [https://wiki.jlab.org/lerf/index.php/File:Vvu.JPG]
 
11/3/2017 - GW magnets were radcon surveyed and moved to storage in BLDG 36, 2 PCs were ordered for PLC programming of Cryo controls & vacuum controls, service request submitted to move rack from free stock to LERF gallery - this is a 36" deep rack for the servers (& free {;-), the network has been created for the project; lclsnet - [https://logbooks.jlab.org/entry/3491092], Active VVUs have been installed on 480 VAC panels [https://wiki.jlab.org/lerf/index.php/File:Vvu.JPG]

Revision as of 11:31, 6 November 2017

11/6/2017 - Draft P & ID drawing done & posted [rev-draft.pdf]

11/3/2017 - GW magnets were radcon surveyed and moved to storage in BLDG 36, 2 PCs were ordered for PLC programming of Cryo controls & vacuum controls, service request submitted to move rack from free stock to LERF gallery - this is a 36" deep rack for the servers (& free {;-), the network has been created for the project; lclsnet - [1], Active VVUs have been installed on 480 VAC panels [2]

11/2/2017 - All of the girders have been removed in preparation of CM move & shuffle [[3]]

11/1/2017 - Last of the cryomodule vacuums & girders have been secured & the clean room has been removed from the vault, the cryomodule & waveguide layout has been taped out on vault floor [[4]]

10/31/2017 - Cable length & routing checks being made

10/30/2017 - Network switches ordered, 2 racks moved to gallery, cryomodule vacuum isolation continues

10/27/2017 - 3 of the 6 vacuum connections for the CEBAF style cryomodules have been secured, had a cable planning meeting

10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process

10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault

10/24/2017 - 480 VAC panels are being mounted in gallery

10/11/2017 - Waveguide design review

10/10/2017 - Clean Hoods have been moved to vault

10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs