Difference between revisions of "Nov 8 2017"

From LCLS-II testing
Jump to navigation Jump to search
 
(7 intermediate revisions by the same user not shown)
Line 2: Line 2:
 
Weekly Reporting
 
Weekly Reporting
 
LERF Conversion
 
LERF Conversion
 +
 
Week of November 2 - 8, 2017
 
Week of November 2 - 8, 2017
  
Issues:
+
==Issues: ==
 
None, installation crews working in CEBAF tunnel this week. This is last week machine will be open so activity will pick up next week with the cryomodule shuffle.
 
None, installation crews working in CEBAF tunnel this week. This is last week machine will be open so activity will pick up next week with the cryomodule shuffle.
LERF accomplishments this week:
+
 
 +
==LERF accomplishments this week:==
 +
 
 +
LERF ICD is has been released for official review. Curt met with the SLAC team Friday and finalized delivery dates for RF hardware and racks.     
 +
 
 +
Dave and Larry now have the needed lengths for ordering the Heliax cable, this will be completed later this week
  
 
Semi-annual Personnel Safety System re-certification complete
 
Semi-annual Personnel Safety System re-certification complete
Line 20: Line 26:
 
Tunnel is all cleaned up and ready for the shuffle, once the CEBAF style modules are moved out the waveguide will be prepared for the new installation.
 
Tunnel is all cleaned up and ready for the shuffle, once the CEBAF style modules are moved out the waveguide will be prepared for the new installation.
  
A 36” deep rack was acquired from ‘free stock’ to hold the 29.5” deep servers
+
A 36” deep rack was acquired from ‘free stock’ to hold the Dell R630, 29.5” deep servers
  
Upcoming Activities:
+
==Upcoming Activities:==
  
 
Cryomodule shuffle and two cryomodule removal from vault
 
Cryomodule shuffle and two cryomodule removal from vault
Line 32: Line 38:
 
Server procurement (2) Dell R630’s
 
Server procurement (2) Dell R630’s
  
 +
----
  
Layout of cryomodules in accelerator vault, girders removed, cable lengths check (tape measure)
+
[[File:Girder6.JPG|thumb|left|alt=A|Layout of cryomodules in accelerator vault, girders removed, cable lengths check (tape measure)]]
 
 
  
New style, commercial Voltage Verification Unit (VVU) for Lock, Tag, & Try on 480 VAC
+
[[File:Vvu.JPG|thumb|left|alt=A|New style, commercial Voltage Verification Unit (VVU) for Lock, Tag, & Try on 480 VAC]]

Latest revision as of 09:35, 8 November 2017

Weekly Reporting LERF Conversion

Week of November 2 - 8, 2017

Issues:

None, installation crews working in CEBAF tunnel this week. This is last week machine will be open so activity will pick up next week with the cryomodule shuffle.

LERF accomplishments this week:

LERF ICD is has been released for official review. Curt met with the SLAC team Friday and finalized delivery dates for RF hardware and racks.

Dave and Larry now have the needed lengths for ordering the Heliax cable, this will be completed later this week

Semi-annual Personnel Safety System re-certification complete

Daily activities can be seen at; https://wiki.jlab.org/lerf/index.php/Daily_Activities

P & ID diagram draft is posted https://wiki.jlab.org/lerf/images/9/94/P_ID_rev-draft.pdf

Safety Assessment document is in progress

The 480 VAC panel work for the SSA power is in progress

Tunnel is all cleaned up and ready for the shuffle, once the CEBAF style modules are moved out the waveguide will be prepared for the new installation.

A 36” deep rack was acquired from ‘free stock’ to hold the Dell R630, 29.5” deep servers

Upcoming Activities:

Cryomodule shuffle and two cryomodule removal from vault

Complete Safety Assessment document

Cable procurement – layout for RF, LLRF, Cryo, & Vac

Server procurement (2) Dell R630’s


A
Layout of cryomodules in accelerator vault, girders removed, cable lengths check (tape measure)
A
New style, commercial Voltage Verification Unit (VVU) for Lock, Tag, & Try on 480 VAC