LERF ICD is has been released for official review. Curt met with the SLAC team Friday and finalized delivery dates for RF hardware and racks. | LERF ICD is has been released for official review. Curt met with the SLAC team Friday and finalized delivery dates for RF hardware and racks. | ||
+ | |||
+ | Dave and Larry now have the needed lengths for ordering the Heliax cable, this will be completed later this week | ||
Semi-annual Personnel Safety System re-certification complete | Semi-annual Personnel Safety System re-certification complete |
Latest revision as of 09:35, 8 November 2017
Weekly Reporting LERF Conversion
Week of November 2 - 8, 2017
Issues:
None, installation crews working in CEBAF tunnel this week. This is last week machine will be open so activity will pick up next week with the cryomodule shuffle.
LERF accomplishments this week:
LERF ICD is has been released for official review. Curt met with the SLAC team Friday and finalized delivery dates for RF hardware and racks.
Dave and Larry now have the needed lengths for ordering the Heliax cable, this will be completed later this week
Semi-annual Personnel Safety System re-certification complete
Daily activities can be seen at; https://wiki.jlab.org/lerf/index.php/Daily_Activities
P & ID diagram draft is posted https://wiki.jlab.org/lerf/images/9/94/P_ID_rev-draft.pdf
Safety Assessment document is in progress
The 480 VAC panel work for the SSA power is in progress
Tunnel is all cleaned up and ready for the shuffle, once the CEBAF style modules are moved out the waveguide will be prepared for the new installation.
A 36” deep rack was acquired from ‘free stock’ to hold the Dell R630, 29.5” deep servers
Upcoming Activities:
Cryomodule shuffle and two cryomodule removal from vault
Complete Safety Assessment document
Cable procurement – layout for RF, LLRF, Cryo, & Vac
Server procurement (2) Dell R630’s