Weekly Reporting
+
 
 +
 
 
WBS 1.01.07 JLAB Management
 
WBS 1.01.07 JLAB Management
 +
 
Week of November 16 - 22, 2017
 
Week of November 16 - 22, 2017
  
Issues:
+
==Issues: ==
 
Short week due to holiday
 
Short week due to holiday
 +
 
Need SLAC to ship SSAs, they need to complete BCR
 
Need SLAC to ship SSAs, they need to complete BCR
Accomplishments this week:
+
 
LERF:
+
==Accomplishments this week:==
 +
 
 
Getting the control room workstations re-networked and set up.  Also Sent email to Matt to find out if anything else is needed on getting that PLC shipped to us asap.
 
Getting the control room workstations re-networked and set up.  Also Sent email to Matt to find out if anything else is needed on getting that PLC shipped to us asap.
 +
 
Lab electricians are being trained to handle the removal of the klystrons from zone 3 and 4. They will also be able to help out on the installation of the new waveguide.
 
Lab electricians are being trained to handle the removal of the klystrons from zone 3 and 4. They will also be able to help out on the installation of the new waveguide.
 +
 
Safety Assessment document is still in progress
 
Safety Assessment document is still in progress
 +
 
Waveguide procurement contract mod complete, the system was re-designed over the past week to utilize newly found 6” bellows and the SLAC miter design. The final price came in at ~$274k
 
Waveguide procurement contract mod complete, the system was re-designed over the past week to utilize newly found 6” bellows and the SLAC miter design. The final price came in at ~$274k
 +
 
Waiting on personnel to do cryomodule shuffle, this is now scheduled for next week
 
Waiting on personnel to do cryomodule shuffle, this is now scheduled for next week
 +
 
Continued work on WIKI site for documentation: wiki.jlab.org/lerf
 
Continued work on WIKI site for documentation: wiki.jlab.org/lerf
Upcoming Activities:
+
 
 +
==Upcoming Activities:==
 
Complete Safety Assessment document
 
Complete Safety Assessment document

Revision as of 10:54, 6 December 2017


WBS 1.01.07 JLAB Management

Week of November 16 - 22, 2017

Issues:

Short week due to holiday

Need SLAC to ship SSAs, they need to complete BCR

Accomplishments this week:

Getting the control room workstations re-networked and set up.  Also Sent email to Matt to find out if anything else is needed on getting that PLC shipped to us asap.

Lab electricians are being trained to handle the removal of the klystrons from zone 3 and 4. They will also be able to help out on the installation of the new waveguide.

Safety Assessment document is still in progress

Waveguide procurement contract mod complete, the system was re-designed over the past week to utilize newly found 6” bellows and the SLAC miter design. The final price came in at ~$274k

Waiting on personnel to do cryomodule shuffle, this is now scheduled for next week

Continued work on WIKI site for documentation: wiki.jlab.org/lerf

Upcoming Activities:

Complete Safety Assessment document