Difference between revisions of "Daily Activities"
Line 1: | Line 1: | ||
− | 12/22/2017 - C37 moved back into place completing the shuffle! [File:Shuff7.jpg] | + | 12/22/2017 - C37 moved back into place completing the shuffle! [https://wiki.jlab.org/lerf/index.php/File:Shuff7.jpg] |
12/19/2017 - Rack bases were delivered | 12/19/2017 - Rack bases were delivered |
Revision as of 09:50, 22 December 2017
12/22/2017 - C37 moved back into place completing the shuffle! [1]
12/19/2017 - Rack bases were delivered
12/18/2017 - Zone 2 base plates have been grouted this AM [2], CryoCon 18i cryodiode controllers have been ordered [3], PC/PLC installed and communicating [4]
12/15/2018 - Clean room draft design sent to manufacturer for quote [5], Dell servers have been delivered!
12/14/2017 - Third review was held for the cryo-Can assembly that ties the CMs to the cryo transfer lines Mounting base plates have been relocated, and surveyed in for C37, zone 2. These are ready to re-grout. PCs are ready for installation & network connection - these are remote accessed machines with no local keyboard & monitor
12/13/2017 - PCs arrived for PLC remote programming, PLC arrived from SLAC to be programed
12/12/2017 - Nuts & bolts for waveguide installation have been delivered
12/6/2017 - Wheels are attached to zone 3 for movement to south wall for storage
12/5/2017 - Girder 1F04 removed for ease of CM move, waveguide gaskets ordered
12/4/2017 - Zone 4 klystrons removed
11/28/2017 - JLab electricians have been trained to remove Klystrons
11/22/2017 - 7/8" Heliax for Total Loss Monitor delivered
11/21/2017 - Waveguide order awarded
11/20/2017 - Waveguide order tweaked to reflect delivery times for SLAC type mitered H & E bends vs standard parts
11/17/2017 - Kevin visited Mega Ind., the waveguide company
11/15/2017 - 7/8" Heliax ordered for Total Loss Monitor (TLM)
11/14/2017 - Heliax PR submitted - 6,000' 3/8"
11/13/2017 - Second Cryo Can design review [6]
11/10/2017 - Waveguide bids have been received
11/9/2017 - Network switch installed and operational in Zone 3 FL03B13
11/8/2017 - Kevin visiting FermiLab - discussions with OPs, CM Assembly, Interlock group & others
11/7/2017 - Semi-annual Personnel Safety System re-certification complete
11/6/2017 - Draft P & ID drawing done & posted [7]
11/3/2017 - GW magnets were radcon surveyed and moved to storage in BLDG 36, 2 PCs were ordered for PLC programming of Cryo controls & vacuum controls, service request submitted to move rack from free stock to LERF gallery - this is a 36" deep rack for the servers (& free {;-), the network has been created for the project; lclsnet - [8], Active VVUs have been installed on 480 VAC panels [9]
11/2/2017 - All of the girders have been removed in preparation of CM move & shuffle [[10]]
11/1/2017 - Last of the cryomodule vacuums & girders have been secured & the clean room has been removed from the vault, the cryomodule & waveguide layout has been taped out on vault floor [[11]]
10/31/2017 - Cable length & routing checks being made
10/30/2017 - Network switches ordered, 2 racks moved to gallery, cryomodule vacuum isolation continues
10/27/2017 - 3 of the 6 vacuum connections for the CEBAF style cryomodules have been secured, had a cable planning meeting
10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process
10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault
10/24/2017 - 480 VAC panels are being mounted in gallery
10/11/2017 - Waveguide design review
10/10/2017 - Clean Hoods have been moved to vault
10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs