(2 intermediate revisions by the same user not shown) | |||
Line 7: | Line 7: | ||
*Cryomodule move of FL02 & FL03 scheduled for 11/2/17 | *Cryomodule move of FL02 & FL03 scheduled for 11/2/17 | ||
*Cooldown of the LERF transferlines, the quarter & zone 2 will be after the CHL trip scheduled for week of November 12??? | *Cooldown of the LERF transferlines, the quarter & zone 2 will be after the CHL trip scheduled for week of November 12??? | ||
+ | |||
+ | |||
+ | [[File:CM tent.jpg|thumb|left|Cryomodule clean tent in place to secure Zone 2 vacuum]] |
Latest revision as of 12:38, 14 October 2017
Minutes from Wed. 10/11/2017 Scheduling meeting:
- Clean room was moved to LERF vault 10/10/17
- CM FL02 upstream end prepared for Vacuum work 10/12/17
- Work on securing cryomodule vacuum will continue over the next weeks, followed by the move of the C20 from zone 4 to zone 2. This will then be re-connected to cryo & RF system
- Kevin & Wes to visit SLAC 10/17-19/17
- PSS certification scheduled for 10/30/17
- Cryomodule move of FL02 & FL03 scheduled for 11/2/17
- Cooldown of the LERF transferlines, the quarter & zone 2 will be after the CHL trip scheduled for week of November 12???