+ | 10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process | ||
+ | |||
+ | 10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault | ||
+ | |||
+ | 10/24/2017 - 480 VAC panels are being mounted in gallery | ||
+ | |||
10/11/2017 - Waveguide design review | 10/11/2017 - Waveguide design review | ||
+ | |||
10/10/2017 - Clean Hoods have been moved to vault | 10/10/2017 - Clean Hoods have been moved to vault | ||
+ | |||
10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs | 10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs |
Revision as of 16:22, 26 October 2017
10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process
10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault
10/24/2017 - 480 VAC panels are being mounted in gallery
10/11/2017 - Waveguide design review
10/10/2017 - Clean Hoods have been moved to vault
10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs