Difference between revisions of "Nov 1 2017"
(Created page with " Weekly Reporting LERF Conversion Week of October 26 – November 1, 2017 Issues: None yet LERF accomplishments this week: Safety Assessment document is in progress The 480...") |
|||
Line 4: | Line 4: | ||
Week of October 26 – November 1, 2017 | Week of October 26 – November 1, 2017 | ||
− | Issues: | + | == Issues: == |
None yet | None yet | ||
− | LERF accomplishments this week: | + | == LERF accomplishments this week: == |
Safety Assessment document is in progress | Safety Assessment document is in progress | ||
+ | |||
The 480 VAC panel work for the SSA power is in progress | The 480 VAC panel work for the SSA power is in progress | ||
+ | |||
Network switches are on order | Network switches are on order | ||
+ | |||
All CEBAF modules and girder vacuums have been secured in preparation for removing girders and two modules as well as shuffling the third from zone 4 to zone 2 | All CEBAF modules and girder vacuums have been secured in preparation for removing girders and two modules as well as shuffling the third from zone 4 to zone 2 | ||
+ | |||
The two racks for network, servers, and vacuum controls have been moved into place in the gallery. Bases are on order then power can be connected. An ATLis has been submitted for connecting 120VAC power to SSAs and to the racks. | The two racks for network, servers, and vacuum controls have been moved into place in the gallery. Bases are on order then power can be connected. An ATLis has been submitted for connecting 120VAC power to SSAs and to the racks. | ||
+ | |||
LCLS-II CM #1 & #2 locations (including waveguide) have been taped out on the vault floor in preparation for cable order – both cryogenic control and RF/LLRF cables | LCLS-II CM #1 & #2 locations (including waveguide) have been taped out on the vault floor in preparation for cable order – both cryogenic control and RF/LLRF cables | ||
− | Upcoming Activities: | + | |
+ | == Upcoming Activities: == | ||
Cryomodule shuffle and two cryomodule removal from vault | Cryomodule shuffle and two cryomodule removal from vault | ||
+ | |||
Completion of the Process & Instrumentation diagram for the cryogenic end can & transferline | Completion of the Process & Instrumentation diagram for the cryogenic end can & transferline | ||
+ | |||
Complete Safety Assessment document | Complete Safety Assessment document | ||
+ | |||
Cable procurement | Cable procurement | ||
+ | |||
Server procurement | Server procurement | ||
− | |||
− | + | ||
+ | Layout of cryomodules in accelerator vault | ||
+ | |||
+ | Vacuum spaces secured for cryomodule shuffle |
Revision as of 10:11, 1 November 2017
Weekly Reporting LERF Conversion Week of October 26 – November 1, 2017
Issues:
None yet
LERF accomplishments this week:
Safety Assessment document is in progress
The 480 VAC panel work for the SSA power is in progress
Network switches are on order
All CEBAF modules and girder vacuums have been secured in preparation for removing girders and two modules as well as shuffling the third from zone 4 to zone 2
The two racks for network, servers, and vacuum controls have been moved into place in the gallery. Bases are on order then power can be connected. An ATLis has been submitted for connecting 120VAC power to SSAs and to the racks.
LCLS-II CM #1 & #2 locations (including waveguide) have been taped out on the vault floor in preparation for cable order – both cryogenic control and RF/LLRF cables
Upcoming Activities:
Cryomodule shuffle and two cryomodule removal from vault
Completion of the Process & Instrumentation diagram for the cryogenic end can & transferline
Complete Safety Assessment document
Cable procurement
Server procurement
Layout of cryomodules in accelerator vault
Vacuum spaces secured for cryomodule shuffle