− | Design water manifold for SSAs & Isolators | + | * Design water manifold for SSAs & Isolators |
− | |||
* Remove waveguide in tunnel from zone 3 and 4 - DONE | * Remove waveguide in tunnel from zone 3 and 4 - DONE | ||
* Finish ceiling layout for waveguide supports - DONE | * Finish ceiling layout for waveguide supports - DONE | ||
− | * Start hanging waveguide in the tunnel | + | * Start hanging waveguide in the tunnel - STARTED |
− | * Get AC power to racks in gallery | + | * Get AC power to racks in gallery - STARTED |
− | * Hang tray over new racks | + | * Hang tray over new racks - STARTED |
− | * Install servers & UPS | + | * Install servers & UPS - DONE |
− | * Move (crane) SSAs to gallery - when will #16 arrive? (March) | + | * Move (crane) SSAs to gallery - DONE - when will #16 arrive? (March) |
* Finalize design & procure false floor parts | * Finalize design & procure false floor parts | ||
* Pull cable... | * Pull cable... |
Revision as of 12:29, 6 February 2018
- Design water manifold for SSAs & Isolators
- Remove waveguide in tunnel from zone 3 and 4 - DONE
- Finish ceiling layout for waveguide supports - DONE
- Start hanging waveguide in the tunnel - STARTED
- Get AC power to racks in gallery - STARTED
- Hang tray over new racks - STARTED
- Install servers & UPS - DONE
- Move (crane) SSAs to gallery - DONE - when will #16 arrive? (March)
- Finalize design & procure false floor parts
- Pull cable...
- Terminate cable...
Cryo racks will be here in March
LLRF Racks arrive in early April
Magnet power supply racks arrive in ???