Line 1: | Line 1: | ||
+ | * Complete PSS connections | ||
+ | * Turn on control power to SSAs | ||
+ | * Finish CM # 1 tunnel waveguide | ||
+ | * Start pulling and terminating cables | ||
+ | * Get Cryo-cons installed and operational | ||
* Design water manifold for SSAs & Isolators | * Design water manifold for SSAs & Isolators | ||
* Remove waveguide in tunnel from zone 3 and 4 - DONE | * Remove waveguide in tunnel from zone 3 and 4 - DONE |
Revision as of 08:31, 27 February 2018
- Complete PSS connections
- Turn on control power to SSAs
- Finish CM # 1 tunnel waveguide
- Start pulling and terminating cables
- Get Cryo-cons installed and operational
- Design water manifold for SSAs & Isolators
- Remove waveguide in tunnel from zone 3 and 4 - DONE
- Finish ceiling layout for waveguide supports - DONE
- Start hanging waveguide in the tunnel - STARTED
- Get AC power to racks in gallery - STARTED
- Hang tray over new racks - STARTED
- Install servers & UPS - DONE
- Move (crane) SSAs to gallery - DONE - when will #16 arrive? (March)
- Finalize design & procure false floor parts
- Pull cable...
- Terminate cable...
Cryo racks will be here in March
LLRF Racks arrive in early April
Magnet power supply racks arrive in ???