(Created page with "Minutes from Wed. 10/11/2017 Scheduling meeting: *Clean room was moved to LERF vault 10/10/17 *CM FL02 upstream end prepared for Vacuum work 10/12/17 *Work on securing cryomod...") |
|||
Line 1: | Line 1: | ||
− | Minutes from Wed. 10/11/2017 Scheduling meeting: | + | '''Minutes from Wed. 10/11/2017 Scheduling meeting:''' |
*Clean room was moved to LERF vault 10/10/17 | *Clean room was moved to LERF vault 10/10/17 | ||
*CM FL02 upstream end prepared for Vacuum work 10/12/17 | *CM FL02 upstream end prepared for Vacuum work 10/12/17 |
Revision as of 12:31, 14 October 2017
Minutes from Wed. 10/11/2017 Scheduling meeting:
- Clean room was moved to LERF vault 10/10/17
- CM FL02 upstream end prepared for Vacuum work 10/12/17
- Work on securing cryomodule vacuum will continue over the next weeks, followed by the move of the C20 from zone 4 to zone 2. This will then be re-connected to cryo & RF system
- Kevin & Wes to visit SLAC 10/17-19/17
- PSS certification scheduled for 10/30/17
- Cryomodule move of FL02 & FL03 scheduled for 11/2/17
- Cooldown of the LERF transferlines, the quarter & zone 2 will be after the CHL trip scheduled for week of November 12???