Daily Activities
12/5/2017 - Girder 1F04 removed for ease of CM move, waveguide gaskets ordered
12/4/2017 - Zone 4 klystrons removed
11/28/2017 - JLab electricians have been trained to remove Klystrons
11/22/2017 - 7/8" Heliax for Total Loss Monitor delivered
11/21/2017 - Waveguide order awarded
11/20/2017 - Waveguide order tweaked to reflect delivery times for SLAC type mitered H & E bends vs standard parts
11/17/2017 - Kevin visited Mega Ind., the waveguide company
11/15/2017 - 7/8" Heliax ordered for Total Loss Monitor (TLM)
11/14/2017 - Heliax PR submitted - 6,000' 3/8"
11/13/2017 - Second Cryo Can design review [1]
11/10/2017 - Waveguide bids have been received
11/9/2017 - Network switch installed and operational in Zone 3 FL03B13
11/8/2017 - Kevin visiting FermiLab - discussions with OPs, CM Assembly, Interlock group & others
11/7/2017 - Semi-annual Personnel Safety System re-certification complete
11/6/2017 - Draft P & ID drawing done & posted [2]
11/3/2017 - GW magnets were radcon surveyed and moved to storage in BLDG 36, 2 PCs were ordered for PLC programming of Cryo controls & vacuum controls, service request submitted to move rack from free stock to LERF gallery - this is a 36" deep rack for the servers (& free {;-), the network has been created for the project; lclsnet - [3], Active VVUs have been installed on 480 VAC panels [4]
11/2/2017 - All of the girders have been removed in preparation of CM move & shuffle [[5]]
11/1/2017 - Last of the cryomodule vacuums & girders have been secured & the clean room has been removed from the vault, the cryomodule & waveguide layout has been taped out on vault floor [[6]]
10/31/2017 - Cable length & routing checks being made
10/30/2017 - Network switches ordered, 2 racks moved to gallery, cryomodule vacuum isolation continues
10/27/2017 - 3 of the 6 vacuum connections for the CEBAF style cryomodules have been secured, had a cable planning meeting
10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process
10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault
10/24/2017 - 480 VAC panels are being mounted in gallery
10/11/2017 - Waveguide design review
10/10/2017 - Clean Hoods have been moved to vault
10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs