10/31/2017 - Cable length & routing checks being made
10/30/2017 - Network switches ordered, 2 racks moved to gallery, cryomodule vacuum isolation continues
10/27/2017 - 3 of the 6 vacuum connections for the CEBAF style cryomodules have been secured, had a cable planning meeting
10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process
10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault
10/24/2017 - 480 VAC panels are being mounted in gallery
10/11/2017 - Waveguide design review
10/10/2017 - Clean Hoods have been moved to vault
10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs