11/1/2017 - Last of the cryomodule vacuums & girders have been secured, cryomodule & waveguide layout has been taped out on vault floor

10/31/2017 - Cable length & routing checks being made

10/30/2017 - Network switches ordered, 2 racks moved to gallery, cryomodule vacuum isolation continues

10/27/2017 - 3 of the 6 vacuum connections for the CEBAF style cryomodules have been secured, had a cable planning meeting

10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process

10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault

10/24/2017 - 480 VAC panels are being mounted in gallery

10/11/2017 - Waveguide design review

10/10/2017 - Clean Hoods have been moved to vault

10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs