Upcoming Activities
Jump to navigation
Jump to search
Installation and welding activities
- Complete PSS connections
- Turn on control power to SSAs
- Finish CM # 1 tunnel waveguide
- Start pulling and terminating cables
- Get Cryo-cons installed and operational
- Design water manifold for SSAs & Isolators
- Remove waveguide in tunnel from zone 3 and 4 - DONE
- Finish ceiling layout for waveguide supports - DONE
- Start hanging waveguide in the tunnel - STARTED
- Get AC power to racks in gallery - STARTED
- Hang tray over new racks - STARTED
- Install servers & UPS - DONE
- Move (crane) SSAs to gallery - DONE - when will #16 arrive? (March)
- Finalize design & procure false floor parts
- Pull cable...
- Terminate cable...
Cryo racks will be here in March
LLRF Racks arrive in early April
Magnet power supply racks arrive in ???