10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process
 +
 +
10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault
 +
 +
10/24/2017 - 480 VAC panels are being mounted in gallery
 +
 
10/11/2017 - Waveguide design review
 
10/11/2017 - Waveguide design review
 +
 
10/10/2017 - Clean Hoods have been moved to vault
 
10/10/2017 - Clean Hoods have been moved to vault
 +
 
10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs
 
10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs

Revision as of 16:22, 26 October 2017

10/26/2017 - The downstream side of zone 2 has gone through the 'slow' bleed-up process

10/25/2017 - Vacuum has been secured from the upstream side of Zone 2 CM in the vault

10/24/2017 - 480 VAC panels are being mounted in gallery

10/11/2017 - Waveguide design review

10/10/2017 - Clean Hoods have been moved to vault

10/9/2017 - Electricians have "Air Gapped" all power connections to FL03 & FL04 CPS & HPAs